Table of Contents
A compressor can continue drawing electricity while unloaded. For a non-production report, match measured kWh to a verified operating-state log. Add the energy from intervals entirely assigned to the unloaded state and retain their corresponding duration. Keep mixed or unknown-state rows separate while including their measured energy in the overall total. A reduction in unloaded-state kWh alone does not establish an air leakage volume or an achieved saving.
Define the hour and the metered equipment
Choose a completed window with a known start and end. Record which production area was inactive, which log confirms it and which other air users could have remained active. A pause in the main production process does not establish zero compressed-air use. Pneumatic equipment in another area or auxiliary processes may still have needed air. If their status is unknown, state that in the report.
Identify the electrical meter boundary. A meter might cover one compressor package with its fans and controls or the whole station with other compressors and a dryer. A station total cannot establish one compressor's electricity use without suitable detail. If the package is already included in the station reading, use its series as a breakdown and count it once in the overall total.
For repeated comparisons, record whether the same circuits were included. If additional cooling or other equipment was added to the meter boundary, preserve a new version of that scope. A comparison of two figures needs evidence of what was measured in each case. The equipment name on a dashboard alone does not identify every circuit included in the reading.
Verify what the unloaded signal means
For a load/unload controlled package, distinguish loaded operation, unloaded operation with the motor running and a stopped motor. Verify the signal meanings from the particular controller's documentation and the facility team's saved explanations. A running label might mean the package is enabled, the motor is turning or another condition. It does not always establish whether air is being delivered.
During unloaded operation, the motor can keep running while the compressor supplies no useful air. After the motor stops, some electrical loads within the package boundary can remain active. Use the measured series for both states, with no assumed zero or universal fraction of nameplate power. A lower electrical trace alone cannot assign a state. That assignment needs evidence of the relevant signal and its meaning.
If the package varies speed or uses a different control strategy, verify the actual states in its archive. Labels from another installation may have a different meaning. When a signal dictionary is missing, the hourly electrical total can remain known while its loaded and unloaded portions remain unverified.
Join the state log and energy records by time
Align time zones, start and end timestamps and the duration of electrical intervals. An event log might record the exact transition time while the energy export provides only five-minute totals. For example, an electrical row from 21:15 to 21:20 spans two states if unloading was recorded at 21:17. One verified transition time does not establish how many kWh belong to each part.
If the mixed interval contains 0.8 kWh, retain that value in a transition column. Dividing it between the states in proportion to minutes requires suitable finer records or a separately justified model. Power could differ before and after the change. The measured 0.8 kWh belongs in the overall electrical total whether or not its state allocation is known.
For each complete interval, check whether one verified state lasted throughout. Include only those rows in both the state's energy sum and its corresponding duration. If a state event is missing, retain the known energy in an unknown-state column. If the electrical reading itself is missing, record a different gap that limits the overall total. The guide to solar monitoring timestamps explains the common time checks.
Worked example with two non-production hours
All figures and conditions in this example are fictional. Consider two completed hours on different days with the same verified package meter boundary. The main production area's log identifies both hours as non-production. Other air users are unverified. Assume usable interval active-energy readings are available and all state boundaries in these two hours align with the electrical interval boundaries.
| Package state | Hour A | Hour B |
|---|---|---|
| Loaded | 10 minutes, 4.0 kWh | 10 minutes, 4.2 kWh |
| Unloaded | 40 minutes, 4.0 kWh | 30 minutes, 3.3 kWh |
| Motor stopped | 10 minutes, 0.2 kWh | 20 minutes, 0.4 kWh |
| Complete hour | 60 minutes, 8.2 kWh | 60 minutes, 7.9 kWh |
The total for hour A is 4.0 + 4.0 + 0.2 = 8.2 kWh. For hour B, 4.2 + 3.3 + 0.4 = 7.9 kWh. Verified unloaded-state energy in B is 0.7 kWh lower, but that state also lasts ten minutes less. Keep both durations beside their energy totals.
Divide unloaded-state energy by its duration in hours. For A, 4.0 ÷ (40/60) gives 6.0 kW of average power over the verified unloaded intervals. For B, 3.3 ÷ (30/60) gives 6.6 kW. The second hour therefore has less unloaded-state energy alongside higher average power over the selected intervals. They describe different quantities and should be presented together.
Dividing by duration does not make the physical conditions of the two hours equivalent. Auxiliary loads, temperatures, pressure and other conditions may differ. Air use is also unknown in the example. The 0.3 kWh difference between the complete hourly totals describes these two observations. It cannot establish why they changed, an annual outcome or a volume of eliminated leaks.
Report coverage and the limits of the result
If other hours contain mixed or unknown-state intervals, record two separate coverage measures. One describes how much time has usable electrical readings. The other describes how much of that measured period has a verified state. The overall total can be complete while the state breakdown remains partial. Known-state energy, transitions and unknown-state energy should reconcile to all known electricity without double counting.
Keep the energy numerator and duration denominator on the same covered intervals. If energy is available for 25 minutes of confirmed pure unloaded operation, divide it by those 25 minutes. Record the rest of the runtime separately. Different coverage between two reports can change averages even when their overall energy totals are almost the same. See the guide to stored data intervals for the effect of coarse readings.
The non-production calendar, compressor loading and air leakage describe different facts. Without verified information about the relevant air users and suitable air-side evidence, an electrical log cannot establish a leakage volume. Preserve the known electrical result and the missing evidence for a technical review. There is no need to assume that every unloaded minute represents avoidable electricity use.
Where one meter covers several compressors, one machine's unloaded log cannot allocate all the kWh. Another compressor may have been loaded at the same time. Without a suitable separate electrical series, retain the group total with the combined known states of its machines. Describing it as one machine's unloaded energy would change the meaning of the measurement. Comparing groups requires records for every machine within their electrical scope.
Distinguish a revision based on better data from a change in consumption. If a more detailed log allows 0.8 kWh to move from the transition column into verified states, the overall known energy remains the same. In the revised report, identify the affected rows and supporting record. If the underlying electrical export was corrected too, show that as a separate revision. This allows another analyst to understand why two report versions differ.
Prepare the record for another reviewer
Provide the original electrical file, event log, signal descriptions and drawing version. In the working table, retain each interval's start and end, kWh, assigned state, supporting evidence and reason for uncertainty. Show the overall sum, energy and covered time for each pure state, mixed rows and missing readings. If a finer log becomes available, revise only the affected rows and preserve the earlier result.
These hours can help explain facility baseload for a solar assessment when their scope is verified. A two-hour report needs a wider context before it can represent an annual load profile. Use the archived data and open questions to discuss a solar site audit. The responsible site team should determine any need for further measurements or work on the compressed-air system.