Table of Contents
Accept a completed iSolarCloud I-V diagnosis report together with a coverage register. Identify which task produced the report, which inverters and strings were included and which findings need follow-up on site. The abnormal string count describes the result available from the selected task. Confirm the coverage before treating it as a conclusion for the entire plant.
Identify the completed task and its report
In the iSolarCloud O&M web interface, IV Curve Online Diagnosis supports diagnosis at unit or selected inverter level. The completed result includes information such as the number of abnormal strings. A generated report can be previewed or downloaded from the report list. Control labels can vary by release and interface language. This workflow uses an already completed task and its report. Feature availability depends on the installed system, supported devices and user access.
Start the review register with the task name, plant, scan type, execution time and the file used. Record the execution and report creation times separately when the file was generated later. This helps align the result with weather, inverter operation and service events. Archive the original and work on a copy. Keep reports generated on different dates separate until you have checked which results and devices were selected.
If two tasks have similar names, open the result and verify the included inverter list. A label such as Roof can refer to an entire building or a single area inspected by service. Compare the equipment scope with the project layout and selected devices. See the guide to iSolarCloud PV monitoring when you need ordinary device states and event context for the same date.
| Task or report evidence | Verify against | What to record |
|---|---|---|
| Unit Scan or Inverter Scan | Agreed work scope and actual device list | Inspection boundary |
| Diagnosis result | Confirmed completion for the relevant device | Result or reason for missing evidence |
| Flagged string | Input identifier and corresponding drawing entry | Physical area and follow-up work |
| File from the report list | Report type, selected devices and task date | File version and creation date |
Build a register of actual coverage
Define the agreed work scope first. Suppose the work order calls for four inverters in one production building and the report includes three. Keep the fourth outside conclusions drawn from those three until there is direct evidence. Record a status for each agreed device. Use an explicit unconfirmed status when no result is available and note any verified reason, such as a device formally removed from the scope.
Count connected strings that were part of the inspection. The maximum number of inverter inputs describes a hardware limit. Acceptance requires the installed arrangement for the relevant period. When the report and drawing use different input numbering, consult the cross-reference and installation records. An accurate count without a reliable correspondence can still send a work order to the wrong string.
If you have two reports, check for overlap before combining totals. One report may cover a whole unit and the other a repeat task on one of its inverters. Record the two executions as separate events. In the coverage register, give each physical string one row even if it was assessed several times. In the incident history, retain the time and result of each diagnostic event so repeated findings stay visible.
Keep only the level of detail that the evidence supports. The drawings might identify two arrays under one inverter while the available summary identifies findings only at inverter level. Record the boundary at that level and open a separate mapping question before assigning a string-specific work order. Use the current drawing convention for roof letters and string numbers so the same identifier continues to mean the same physical location.
If the work scope excludes two inputs documented as unconnected, keep their plan reference separately. A connected input with no result requires a different status. This makes it possible to explain why one row was excluded from the denominator while another remains within the agreed scope and needs follow-up.
Reconcile a fictional set of results
Suppose the agreed scope contains 24 connected strings across four inverters. You can confirm a result for 18, of which three were flagged. Coverage is 18 of 24, or 75%. The flagged share of confirmed results is three of 18, approximately 16.7%. The remaining six have unconfirmed results. Dividing three by 24 would describe a ratio to the intended scope rather than the flagged share of actually confirmed results.
Suppose one of the three flagged strings is included in a later task and is flagged again. The register contains one physical string and two diagnostic events. Retain both results under the same string identifier. If the later task yields no result for that same string, keep the original flag with its date and mark the repeat check as unconfirmed. The next technician can then see which evidence supports the follow-up.
The same method applies to a smaller plant with a single inverter. If the report covers every connection in the agreed scope, record how you verified that. When the interface gives an abnormal string count without showing enough detail to determine coverage, keep the denominator unknown. Report the count and known boundary without a calculated percentage based on unverified inputs.
When the on-screen total and downloaded detail disagree, verify that they refer to the same task, selected devices and report type. Retain both values with their origins while the discrepancy is open. Ask the diagnostic owner to confirm the scope if a filter or the selection is missing. Use only the verified subset for decisions until the two views can be reconciled.
Record the task time separately from the file creation and delivery dates. A report emailed on Monday can represent work executed on Friday. Weather or inverter history belongs to the diagnostic time, while document version control uses the time and revision of the file the reviewer actually saw.
Prepare a service task from each finding
For each flag, record the plant, inverter, input or string, diagnosis date, original file and result text. Confirm its physical position against the drawing before raising a work order. Add relevant observations such as documented roof work or a contemporaneous fault message. A diagnostic flag identifies a candidate for investigation. The physical cause requires corroborating evidence and the appropriate site inspection.
The separate article on reading a PV I-V curve test report explains how to evaluate the measurement conditions and available reference. Where a report omits the data required to reproduce the curve, avoid assigning a precise cause from the summary count alone. Compare tasks over time only after verifying the same area, string arrangement and suitable operating conditions. Link a repeated check to the prior task and record what was actually rechecked.
Close the report after verification
If the findings require PV maintenance, share the report, mapped drawing and list of unresolved positions. For a shift handover, distinguish accepted results, planned inspections and portions outside confirmed coverage. Preserve the next inspection record separately from the original platform export. The team can then determine whether the original issue was addressed using the relevant record.
Before closing the work order, ask the reviewer to select one flagged string and trace it from the PDF to the verified electrical position. Have them repeat the exercise on one string with missing evidence. The first check tests the link between the diagnostic tool and field work. The second tests whether the report has silently turned absence into satisfactory passage. If it fails either check, repair the mapping or narrow the accepted scope before using the summary for a fleet decision.