Generator recovery band and time: reading acceptance
Technology

Generator recovery band and time: reading acceptance

Read voltage and frequency dip depth and recovery against agreed criteria for a defined generator load step.

ReadAll Articles
Diesel generator and monitor with voltage and frequency response curves

Table of Contents

Read four results from one defined step

A generator acceptance chart should answer four separate questions: how far voltage fell, how far frequency fell, and how long each took to return to its agreed band. A dip within its limit does not automatically mean that recovery was fast enough. Reconcile the test conditions, measurement point and four criteria with the agreed acceptance document.

Start with the step and the reference values. Then read the lowest voltage and frequency on their respective traces, and compare each with its own dip limit. Finally, identify the last return into each recovery band during the agreed observation interval and compare the elapsed times with the applicable limits. Keep a separate status for each result and leave the event unresolved if the trace, criteria or test conditions are incomplete.

This guide concerns one sudden increase of a defined load on an isolated diesel generator. It is a way to review a report, not a switching procedure or a generator selection calculation. A complete acceptance programme can contain other steps and observations. The generator load-bank acceptance guide covers that wider package and its records.

Identify the event before reading the curves

Find the generator and report revision, the date, the measurement location and the event label. Check that the recorded arrangement matches the agreed configuration and operating mode. The generator terminals and a distant load are different measurement points. Record whether voltage refers to a phase pair or phase to neutral and which channels are included. Confirm the frequency channel and units as well.

The load description needs its initial and final levels, the size of the change, the power basis and the type of load. A change from 20 to 60 kW is a 40 kW step, not a 60 kW step. If a percentage is used, identify its denominator and rating. Kilowatts, kilovolt-amperes and current are different quantities. Power factor and the behaviour of the actual load also belong in the test description where relevant.

Check whether the trace covers the period before the event, the full disturbance and the agreed observation interval afterwards. It should identify the time origin and show the channels on an understandable time scale. Ask the reporting team how the instrument detects, calculates and records each value, whether the resolution is adequate, and how uncertainty is addressed. A chart that begins after the event or contains a gap around the minimum may not establish the lowest value.

Separate the lowest point from the recovery band

The dip is the difference between a defined reference and the minimum during the event. A common presentation uses a percentage of the reference, but the contract or test specification must define that reference. A 400 V nominal base and a pre-event value of 396 V produce different percentages for the same minimum. Preserve both references and the specified formulas for voltage and frequency.

The recovery band is a range around a stated target, such as a hypothetical 400 V plus or minus 2%. Its boundaries are 392 V and 408 V. A recovery time also needs a start and an end definition. The project may use the load application as the start, while another document may define it differently. Read the definition rather than comparing times from different reports as if their clocks started together.

For the example below, recovery means the first entry after which the trace remains inside the band for the rest of the agreed observation interval. A brief crossing followed by another departure is not the final re-entry under that definition. A report cannot establish what happens beyond its recorded interval. If the agreed method requires a different dwell period or end rule, apply that rule instead and retain its wording with the result.

Work through an illustrative chart

Suppose a fictional acceptance document defines a single resistive step from 20 to 60 kW for an isolated set. The 40 kW increase is 40% of a hypothetical 100 kW reference rating. It states nominal references of 400 V line to line and 50 Hz. The chart is assumed complete and suitable for the agreed method, with the step applied at zero seconds and observation continuing to six seconds. These are teaching assumptions, not a performance claim or recommended limits.

The fictional criteria allow a voltage dip of at most 10% and a frequency dip of at most 4%, both relative to nominal. Voltage must re-enter and remain in its 392 to 408 V band within 2.5 seconds. Frequency must re-enter and remain in its 49.5 to 50.5 Hz band within 2.2 seconds. Both times start at the load step. The observed minima are 368 V and 48.5 Hz. The voltage trace first enters its band at 1.4 seconds, leaves again, and finally re-enters at 3.0 seconds. Frequency finally re-enters at 2.0 seconds. Under this fictional agreement the uninterrupted confirmation window ends at 6.0 seconds, giving 3.0 seconds in band for voltage and 4.0 seconds for frequency.

CheckCalculation or observed resultFictional criterionStatus
Voltage dip(400 - 368) / 400 = 8%At most 10%Meets
Frequency dip(50 - 48.5) / 50 = 3%At most 4%Meets
Voltage recoveryFinal entry at 3.0 sWithin 2.5 sDoes not meet
Frequency recoveryFinal entry at 2.0 sWithin 2.2 sMeets

For voltage, the permitted minimum on this particular basis is 400 × 0.90 = 360 V. The observed 368 V is above it, so the depth meets the fictional criterion. Frequency may fall to 50 × 0.96 = 48 Hz under its separate fictional depth criterion. The observed 48.5 Hz is above that boundary. Neither calculation establishes the recovery result.

The first voltage entry at 1.4 seconds is not the answer because the trace leaves the band again. The final entry at 3.0 seconds is later than 2.5 seconds. Therefore voltage recovery does not meet the fictional criterion even though the other three checks do. The result for this one event is not an overall acceptance of the generator. The record should show the failed item and the responsible review, rather than averaging four results into a pass.

When a result cannot be reconciled

If only a minimum appears in a summary, request the underlying time trace and the definition of the reported value. If only a later stable reading is available, it does not reveal the true minimum or the last band entry. Likewise, a chart with a slow or averaged channel may miss a short excursion. The reporting team should state whether the available recording supports the specific acceptance calculation.

If the report gives a recovery time but omits the band or start point, leave that check open. A return to within 5% and a return to within 2% are different events. A time measured from the minimum is not necessarily the time measured from load application. Ask for the original definitions and the data needed to recalculate, rather than substituting the first crossing visible on an unlabeled plot.

Where a criterion refers to a performance class or standard, request the applicable edition, the exact agreed test and the clause or specification used by the responsible engineer. A class name alone does not provide the full test conditions on the chart. Different applications can also have additional project requirements. Do not import generic catalogue limits.

The measured step is also not interchangeable with a different customer load. A resistive load bank and a motor or electronic input can present different transient behaviour. The generator voltage response guide covers evidence for diagnosis. Here, the acceptance evidence stays specific to the measured step and agreed conditions.

Close the record with the responsible team

Keep the signed or agreed acceptance criteria alongside the chart, raw record and equipment configuration. Record initial load, final load, reference rating, measurement point, time origin, band boundaries, observation interval and each of the four results. Include units and percentage bases. If a channel, timestamp or criterion is missing, mark the relevant status as pending and name the document needed to resolve it.

Ask the responsible engineer to explain discrepancies, instrument limitations and any alarms before an acceptance decision. If a result does not meet the agreed limit, record the disposition and any separately agreed follow-up. A later trace needs its own conditions and status. Preserve the original instead of replacing an unfavourable result with a later one that happens to look better.

Finally, distinguish the result from the whole commissioning decision. This worksheet covers a single positive step and only voltage and frequency depth and recovery. It does not assess load removal, sustained loading, protections, fuel, cooling or every connected device. The owner receives a useful, reviewable outcome when each criterion has its evidence and unresolved items have an owner, rather than a single unexplained tick on a graph.