Check the internal arc classification, or IAC, against the actual switchgear configuration, declared sides and room conditions. A code such as AFLR needs the complete classification and the associated test current and duration. Where the tested assembly and installation assumptions are not identified, the abbreviation alone cannot resolve the purchasing decision.
Compare the design requirement, the supplier's offer and the applicable drawing. When the same offer contains alternatives, find the classification evidence for each. Treat access restrictions and operation as separate site responsibilities. The comparison here concerns documentation supplied for the equipment and the arrangement in which it will be used.
Break the designation into its actual fields
IAC describes an internal arc classification under specified test conditions. In a commonly used designation, A represents a restricted accessibility category. F, L and R describe the front, lateral and rear sides included in that classification. The declaration also refers to test current and duration. Keep these fields together with the configuration to which they apply.
Check which face the manufacturer defines as front. A project plan may show the assembly from a different orientation than a technical drawing. If the location of the staff passage changes, the relevant side under the classification can change as well. A picture from a leaflet without an approved orientation cannot confirm which face is exposed to the passage.
Several other ratings can appear on the same page. The IP rating, a service continuity category and main circuit characteristics each have their own meaning. They do not establish the internal arc classification. Maintain a separate field for every characteristic, its exact basis and the part of the quotation that it applies to.
The test current and duration are linked to the declared IAC. They cannot be replaced by the continuous load current or a different short-time withstand rating. Multiplication of current and time alone does not prove coverage of a different pair of values. Ask for the declaration applicable to the agreed equipment and room configuration.
Identify the limits of the tested assembly
One product family can include different enclosure options, bay selections and exhaust arrangements. The available classification may depend on the configuration and the compartments to which it applies. Reconcile the declared scope with the exact code in the offer. Treat a family label as a starting point for evidence, with the purchased build still to be verified.
For a row of cubicles, highlight the end bays and any transitions between different assemblies. A revised row can introduce hardware or layout changes that need confirmation against the tested representative configuration. Ask which options are included in the declaration and whether an appendix limits the result to a specified variant or compartment.
| Review item | Keep from the offer | Verify in the supporting records |
|---|---|---|
| Assembly | Bay schedule and configuration code | Identification of the tested or covered build |
| Accessibility | Complete IAC designation | Applicable category and its boundary |
| Faces | Declared F, L and R as applicable | Orientation relative to actual passages |
| Test parameters | Current and duration as one declared pair | Matching classification evidence |
| Room arrangement | Plan and exhaust concept | Approved conditions for the supplied assembly |
| Evidence | Report and referenced appendices | Included compartments and options |
Compare the room with the documented arrangement
Manufacturer documents can state room or installation conditions for a particular classification. These may include the enclosure arrangement, boundaries and the way gases from an internal arc are directed. Give the designer the current room plan and relevant manufacturer drawing so the configurations can be compared. This is a review of evidence rather than an instruction to arrange a room.
Mark the proposed front, side and rear passages on the project plan. Ask how each passage relates to the documented accessible faces. Space to service a cubicle does not, by itself, verify the classification for a person present there. The responsible team also checks how the proposed exhaust arrangement relates to partitions and the approved layout.
Make the comparison against the current revision. A ventilation change, new cable route or substituted panel can make an earlier layout obsolete. For example, one drawing may refer to a duct that is missing from the final supply schedule. Identify the missing component or approval as a specific issue instead of treating a previous report as coverage for the new drawing.
If access is limited to only selected staff, record how the project defines the relevant area and who maintains those access conditions. An alphabetic marking is an equipment classification field. The facility's real access arrangement needs separate confirmation. Keep it traceable so a later change of building use can prompt another review.
Work through two hypothetical options
Imagine a fictional offer with two alternatives. The first declares A-F with a matched drawing. The facility plan also shows a rear passage with no documented review. The second declares A-FLR but has no attached drawing for its proposed exhaust configuration. The first leaves a question about the rear passage. The second leaves a question about the conditions of the claimed configuration.
Use different requests for the two cases. Ask the designer to check actual access faces for the first option. Ask the second supplier for the appendix to the classification evidence and the matching layout. The example uses labels to demonstrate the review process and contains no equipment rating or class recommendation.
If the response covers a product family only, ask for the full ordered designation and the applicable item in the manufacturer's documentation. A single cover letter can refer to several arrangements. Close a review issue only after identifying which one will actually be supplied with the listed components.
Keep other protection evidence in separate records
The guide to air and gas insulated switchgear describes the differences between assembly choices. An insulation technology does not establish an internal arc classification for all equipment using it. The classification evidence comes from the documented assembly and conditions, not the broad category of insulation.
An arc protection event record explains which detector and trip outputs were observed. Breaker trip circuit supervision concerns a separate part of that operating path. The equipment's IAC instead concerns its tested conditions of classification. A record that an active protection device is fitted does not substitute for the classification documents. Keep the design and evidence for both questions available to the engineers.
Confirm who handles changes affecting these two areas. A modification to the enclosure or room may need an applicability review. A change to the logic or supervision may need a different review. Collect approved revisions and ensure that any summary identifies which question the author of the supporting document has already answered.
Keep configuration changes traceable
When a supplier proposes a substitution, retain the old and new codes, drawing revisions and affected compartments. Ask whether the previously reviewed classification evidence applies to the new build and layout. A short finding that identifies the requested clarification is useful even before the question is closed. Keep it with the earlier evidence until the approved documentation is issued.
A room plan may also move independently of the order. If the equipment stays the same but a passage or partition moves, review the interface again. The issue log should identify who supplies the revised drawing and which condition needs another comparison.
Prepare the record for acceptance
Retain the exact equipment revision, complete IAC, room drawing, exhaust configuration and the status of supporting evidence. If delivered equipment differs from the accepted arrangement, record the difference and obtain a written assessment before clearing the issue. Attach the final supply schedule and the drawing the actual comparison used.
During commercial solar design, record which team checks documentation for the switchgear, which team assesses the room, and who signs for the final interface. Applicable requirements depend on the actual equipment, the facility and access conditions. A clear action list allows unresolved items to remain visible until their applicable evidence is available.