A solar plant may generate electricity during commissioning while work needed for its intended operating mode is still underway. If the company sells part of that output, the finance team needs separate assessments of the sale, the cost of the electricity sold, and the cost of preparing the plant for its intended use. The workflow below is for a business reporting under IFRS. The example assumes the business could sell the electricity in that period and has supporting records for the sale.
Establish the condition of the plant when it generated electricity
Start by describing how the business intends to operate the plant. Identify the functions, equipment, and work still open at the time of generation. An inverter might produce electricity in a test mode while the team is still checking a control feature needed for the intended configuration. The technical record should identify the work relevant to readiness and say when the team completed it.
Paragraphs 16, 17, and 20 of IAS 16 connect preparation costs with bringing an asset to the location and condition necessary for operation as intended by management. Testing that the asset functions properly can be a directly attributable cost. For an actual invoice, substantiate the work and identify the asset to which it belongs. See when a solar asset is ready and depreciation begins for a separate review of the date.
Compare the technical conclusion with work logs, acceptance records, and the list of open items. The first monitoring reading or the day an invoice is paid can help establish the sequence. Readiness depends on the facts and the intended operating mode. If a part of the plant can operate independently, establish which asset the team is assessing. A plant-wide meter reading may hide differences in the readiness of its parts.
Separate the sale from the cost of preparing the asset
Paragraph 20A of IAS 16 covers items produced while preparing property, plant and equipment for its intended use. The entity recognizes the proceeds from selling those items and their cost in profit or loss under the applicable standards. It measures their cost under IAS 2. The plant's own cost calculation includes eligible preparation expenditures and accounts separately for costs measured for items produced and sold.
For the sale, start with commercial meter data and supporting documents. Distinguish gross generation, auxiliary consumption, on-site business use, and the quantity confirmed for sale. Reconcile those measures over the same time intervals and in the same units. Use the volume supported by the transaction rather than projecting revenue for electricity used on site. The handbook material on commercial metering and settlement inputs addresses the source data that may be relevant.
Next, check the allocation of costs. Ask which work was needed to prepare the plant for its intended operation and which costs entered the measurement of the output sold. If one contract covers both, keep the itemized evidence and the basis used to assign the individual costs. Reconcile the lines once across both calculations. If the contractor has yet to provide sufficient detail, assign an owner to obtain it before signing off the totals.
For a reconciliation, suppose a generation meter shows 4,600 kWh during the test and settlement documents show 4,000 kWh sold. Trace the difference at the same measurement boundary and time intervals. Some electricity may have been used on site or recorded at a different boundary. Use the supported sale of 4,000 kWh in the calculation below. Preserve any unresolved difference in the metering workpaper.
A worked calculation for one period
Suppose the supported cost of the unfinished solar plant before testing was UAH 1,200,000. During testing the company supports UAH 60,000 in directly attributable preparation costs that meet the recognition criteria. Separately, the company measures UAH 9,000 as the cost of the electricity sold using the applicable IAS 2 requirements. Each cost appears in only one of those two amounts.
The company sells 4,000 kWh in accordance with the contract and recognizes revenue of UAH 16,000. These amounts are hypothetical. They establish the arithmetic and do not set a tariff, transaction model, or real cost for Ukraine. In the example the revenue and related costs fall in a single reporting period and no other event changes the cost of the asset.
| Event | Illustrative amount | Where to reconcile it |
|---|---|---|
| Asset preparation cost already accumulated | UAH 1,200,000 | Construction asset register |
| Eligible costs of necessary testing | UAH 60,000 | Itemized preparation records |
| Revenue from electricity sold | UAH 16,000 | Sale documents for 4,000 kWh |
| Cost of electricity sold | UAH 9,000 | Accounting workpaper for the output |
| Plant cost after adding the preparation costs | UAH 1,260,000 | Updated asset register |
| Sales result from the two lines shown | UAH 7,000 | Revenue less the related cost |
The asset cost is 1,200,000 + 60,000 = UAH 1,260,000. The difference between revenue and cost of sales is 16,000 − 9,000 = UAH 7,000. If a previous workpaper deducted UAH 16,000 of revenue directly from the plant, it would show UAH 1,244,000. The team can use the difference to find the revenue line and correct where it was applied.
Reconcile the evidence with reporting dates
Record the date of the test, meter data intervals, the period of the supported sale, and settlement status. A counterparty statement or payment may arrive after the test. Keep the actual and expected payments in the cash forecast. Use the applicable recognition standards and facts of the sale for financial reporting. That helps explain why a sale can have been recognized while payment remains outstanding.
Check for overlap with work performed after the plant became ready. If it could already operate as intended, a subsequent period of lower production or lower demand calls for a separate assessment. Paragraph 20 of IAS 16 ties the end of adding costs to the readiness of the asset. Identify what was done after that point and under which agreement. See engineering and accounting records for a solar plant for a structure for the evidence.
If electricity was generated before and after readiness within one settlement period, preserve an intermediate cut-off in the data. Use time intervals that can be reproduced from the meter log or other supporting records. Match the time stamps with the acceptance records and operating mode and use consistent measurement definitions. For plants commissioned in stages, show which part of the plant each group of readings covers.
Close the accounting workpaper
- Asset identifier, intended operation, and technical evidence of readiness.
- Test results and meter intervals supporting the amount sold.
- Sale documents, actual cash, and outstanding settlement balances.
- The cost calculation for the items sold and a separate asset preparation calculation.
- Open discrepancies with a named owner and supported resolution.
Paragraph 74A of IAS 16 calls for disclosure in the relevant circumstances of proceeds and cost for items that are outside ordinary activities, and the line items where they appear, when not presented separately in the statement of comprehensive income. Assess the disclosure against the actual business and the transaction. The solar project funding budget can retain its own line for actual cash movements. Use the accounting workpaper to explain the financial reporting amounts.
The conditions for operating a plant before its intended use depend on the project documents, operating permissions and the local installation. Confirm the measured volume and the basis of the sale before adding numbers to the financial model. The worked example shows how to reconcile amounts that have already been substantiated and preserve the boundary between the asset and the result of selling production.