Plan milestone payments for a solar project alongside the work results, supporting documents and available cash. For every amount, identify the recipient, payment event, evidence, deadline and person responsible for checking it. Then place all payments in one calendar, including expenses outside the main contract.
The calendar shows how much cash is needed before generation begins and helps distinguish an advance from payment for an accepted result. The example below is educational. Its amounts and dates are invented and are neither a market offer nor recommended payment percentages.
Start with a consistent procurement scope
One offer may include equipment, installation and commissioning, while another covers supply alone. Before signing, compare the specification, completeness, boundaries of work, schedule and responsibility for delivery and unloading. List the business's own work, other contractors and payments that still need confirmation separately.
For example, if the contractor supplies modules and an inverter but roof strengthening is ordered separately, its price and timing still affect the cash requirement. The 100 kW solar budget guide helps compare scope. Use the same pricing date and tax basis when comparing offers. Do not treat an amount with an unknown scope as final.
List the contracts for design, equipment, installation, site preparation and other necessary work. Record the counterparty and amount for each one, together with the version of the agreed specification. If the customer purchases some equipment directly, related transport, storage and handover to installers are not necessarily included in that price.
Connect each payment to an identifiable event
A date answers when payment is planned. An event explains what it is for and what must happen first. An initial amount might be an advance after signing. Another payment might depend on delivery of a defined set of equipment, while a later one could depend on an agreed work result. The parties establish the actual terms in their documents, not by adopting a generic sequence.
Describe each result so both sides can check it. The phrase “equipment is ready” needs clarification: does it mean readiness at a warehouse, handover to a carrier or receipt on site? Delivery of one inverter does not necessarily mean delivery of the complete set. For installation, identify the portion of work, its boundaries and how observations are recorded.
Agree which record supports the event, who prepares it, who checks it and how comments are communicated. An invoice states an amount requested for payment, but it does not itself replace a completeness or quality check. A shared version register helps when preparing business solar project documents.
Put evidence and responsibility in a matrix
| Event in the example | What the customer checks | What the parties need to agree |
|---|---|---|
| Signing and advance | Contract scope, amount, invoice and authority | Advance amount, date and how it is accounted for in later settlements |
| Equipment delivery | Quantities, models, packaging condition and accompanying records | Who receives the goods and how shortages or damage are recorded |
| Installation stage | Scope completed and results of agreed checks | Stage record, observations and timing of corrections |
| Handover | Agreed checks, drawings, access and document package | Final payment conditions and treatment of open items |
This is a working example, not a mandatory set of milestones for every contract. Add columns for the planned date, actual date, amount, document reference and the responsible person's decision. Mark whether a record has been received, checked, accepted or needs clarification. One tick should not stand for all four states.
An illustrative cash calendar
Assume a business plans a solar plant without storage. The fictional main contract is UAH 2,000,000, and separate customer-side work costs another UAH 200,000. For simplicity, all figures use the same basis excluding VAT. VAT cash movements, financing and price changes are excluded from this example, although they may matter materially in a real transaction.
Under the invented main-contract calendar, an advance of UAH 600,000 falls in month one, UAH 800,000 follows the agreed delivery in month two, and UAH 600,000 follows acceptance of the agreed result in month four. Separate work is paid in amounts of UAH 120,000 in month two and UAH 80,000 in month three. For this example, start-up is at the beginning of month five. This assumption is not an installation-duration forecast.
| Month | Main contract, UAH | Separate work, UAH | Monthly total, UAH | Cumulative, UAH |
|---|---|---|---|---|
| 1 | 600,000 | 0 | 600,000 | 600,000 |
| 2 | 800,000 | 120,000 | 920,000 | 1,520,000 |
| 3 | 0 | 80,000 | 80,000 | 1,600,000 |
| 4 | 600,000 | 0 | 600,000 | 2,200,000 |
The main contract adds up to 600,000 + 800,000 + 600,000 = UAH 2,000,000. Including the separate work, the amount needed before start-up is UAH 2,200,000. The largest monthly total of payments is UAH 920,000. It is not the same as the need for additional financing, which depends on the opening balance and the business's other receipts and payments.
Assume UAH 1,200,000 has been set aside for the project at the start of month one, with no other receipts or payments in this separate illustrative account. After month one, UAH 600,000 remains. The UAH 920,000 total of payments in month two exceeds that balance by UAH 320,000. Across the full schedule, without additional receipts, the total shortfall is 2,200,000 - 1,200,000 = UAH 1,000,000. This is not a loan calculation or advice to borrow.
Reconcile advances with later payments
Distinguish the date cash was transferred from the date it was recognized in the settlement with the counterparty. In the example, the advance is part of the main contract price, so it is counted only once in the total. Ask the finance team to agree a reconciliation format with the counterparty and keep payment evidence with the relevant contract.
If equipment arrives in parts, create a separate delivery register showing each item, agreed quantity, actual quantity, receipt date and observations. Whether the next payment is due depends on the agreed trigger. Do not treat a partial delivery as a complete one or assume that payment is automatically deferred without checking the contract.
Suppose 70 of 100 hypothetical units are received. The calculation 70 / 100 = 70% describes quantity. It does not establish 70% of the value or the payment due if the items differ. Item prices and actual terms are needed. Record the discrepancy, name an owner and schedule the next check.
Test delay and scope changes
Create a second calendar in which delivery moves by one month. Do not simply move every row: check which activities depend on delivery, whether a separate contractor's payment remains due and when site-preparation funds are needed. If start-up also moves, expected savings should not remain in the original month without a revised basis.
Create a separate line for additional work, with a description, amount, source of the offer and approval status. Do not count the same change both in the original price and in a reserve. A liquidity reserve also differs from an agreed price. It shows the funds a company chooses to hold for uncertain expenses, not proof that those expenses will arise.
Compare versions by total amount, largest payment in a period, cash required before start-up and unresolved conditions. Record who may approve a change, what document records it and how the calendar will be updated. For a disputed milestone, do not replace the actual agreement with an assumption that the deadline moves automatically.
When several payments fall in the same week, a monthly total may hide a temporary shortage. Convert the next few rows to a weekly or daily plan and record when funds are expected to arrive. If an incoming payment is later than an outgoing one, the monthly balance can be positive even though cash runs short in between. Compare the lowest balance in the period with the company’s agreed internal reserve and assign responsibility for updating dates.
Check the plan with the right people
The finance team needs dates, currency, tax basis, funding sources and the business's other payments in the same periods. An accountant should assess the tax treatment and documentation of the particular transaction. Give the legal adviser the draft contracts and the agreed event matrix, including proposed rules for schedule changes, acceptance, security and resolving disagreements.
The technical owner checks the actual result: delivery scope, work completed, agreed tests and handover records. Include monitoring access, drawings and instructions where the parties have agreed to provide them. Keep signed records together with the specification version to which they relate. A document register is useful only if someone owns each missing item and can confirm its status.
After start-up, the construction payment calendar does not replace an operating-cost or debt-service plan. If the project uses a loan, separately compare loan payments with seasonal savings. Before deciding, identify unknown amounts and agree who will verify each one and by when.
To discuss project scope and boundaries, explore solar services.