A pump and solar power system can operate together when the agreed water-delivery schedule coincides with generation. An existing reservoir may sometimes allow part of the pumping to move in time, while a variable-speed drive may change the pump's operating mode. Neither capability alone proves that the required water volume will arrive when needed.
Start with an interval water balance, minimum reserve and the limits of pipes and equipment. Only then compare permissible modes with the PV profile. The example below is illustrative: it helps frame questions for a designer but does not specify water supply for a particular site.
Define the water-delivery task
Establish how much water each user needs, when it is needed and the pressure and quality requirements. Mark periods when delivery cannot stop and any permitted pauses confirmed by the process owner. Irrigation also needs an agreed calendar and requirements for actual watering, not just an electrical schedule.
Check source availability across seasons, agreed withdrawal modes and operating conditions. Production plans can change, so high demand needs a separate scenario. Do not assume a daily volume can be delivered in any number of hours: pump, network and receiving-reservoir limits determine the feasible flow.
Where several pumps exist, record their real combinations, sequence and necessary auxiliaries. Electrical and hydraulic diagrams should describe the same configuration. One motor's rated power does not describe the entire process or the volume actually moved.
Collect data on one timeline
| Group | Data | Purpose |
|---|---|---|
| Water users | Volume and timing, pressure and quality requirements | Check that needs are met in each interval |
| Reservoir | Operating level limits, required reserve and measured level | Assess available water and free capacity |
| Pumping station | Flow, pressure, pump states, electrical power and drive limits | Check feasible pumping schedules |
| Electrical side | PV generation, other loads, limits and measurement times | Compare available energy with pump demand |
Record the source, time zone, interval and units of every series. Do not convert a level in metres to a volume in cubic metres without the relationship for the reservoir's actual shape. Starts or pressure fluctuations may require more detailed readings than hourly averages.
When PV already operates at the site, grid import does not equal all consumption. A consistent picture also uses generation and other source data. General electrical profile preparation is explained in commercial solar sizing using a load profile.
For each sensor record its location, check date and the person responsible for readings. Preserve original data with an explanation of gaps.
Also mark whether a meter records volume at the reservoir inlet or at the outlet to users. If metering points differ, record every intermediate branch. Leave an unavailable series unknown rather than substituting zero, so an unbalanced section is visible and the necessary measurement can be arranged.
What reserve is actually available?
A reservoir's total geometric volume is not necessarily its usable reserve. Establish permitted lower and upper limits, water needed for other tasks and the actual starting level. Agree what happens on sensor failure, insufficient inflow or an excessive level.
In a simplified balance, end volume equals starting volume plus pumped inflow minus user withdrawals. If other flows, losses or leaks matter, add them as separate lines. Calculate intervals in sequence: the previous end value becomes the next starting value.
Actual flow depends on the pump's operating point and the network. Average volume does not establish permissible pressure at each user. Hydraulic design, protection and safe operation must be assessed for the real system, not from the teaching table below.
Two illustrative four-hour schedules
Compare two invented schedules for one reservoir. It begins at 100 m³, with an agreed minimum of 40 m³ and an upper operating limit of 160 m³. Users withdraw 20 m³ each hour, with other inflows and losses assumed zero. The baseline receives 20 m³ each hour; the alternative shifts inflow to hours two and three. These volumes are exercise inputs, not established equipment capabilities.
| Time | Withdrawal | Inflow: baseline / alternative | End stock: baseline / alternative |
|---|---|---|---|
| 08:00-09:00 | 20 | 20 / 0 | 100 / 80 |
| 09:00-10:00 | 20 | 20 / 40 | 100 / 100 |
| 10:00-11:00 | 20 | 20 / 40 | 100 / 120 |
| 11:00-12:00 | 20 | 20 / 0 | 100 / 100 |
In the alternative's second interval, 80 + 40 - 20 = 100 m³. Both cases receive 80 m³ and deliver 80 m³, beginning and ending at the same 100 m³ stock. End values stay within the assumed limits. They do not show the minimum and maximum within each hour or establish pressure, water quality or feasible pump flow.
For arithmetic only, assume pumping each 20 m³ requires 10 kWh in either mode, with no other electrical demand inside this boundary. Each schedule then uses 40 kWh. Solar energy available to the pumps after other loads is hypothetically 0, 30, 30 and 0 kWh in the four hours. For this illustration, assume constant generation and pump power within each hour.
| Time | Available solar | Pump: baseline / alternative | Coincident solar use: baseline / alternative |
|---|---|---|---|
| 08:00-09:00 | 0 | 10 / 0 | 0 / 0 |
| 09:00-10:00 | 30 | 10 / 20 | 10 / 20 |
| 10:00-11:00 | 30 | 10 / 20 | 10 / 20 |
| 11:00-12:00 | 0 | 10 / 0 | 0 / 0 |
Under these assumptions, coincident use is 20 kWh for the baseline and 40 kWh for the alternative. The 20 kWh difference is a teaching result, not a forecast of savings or actual operation. It depends on the assumed uniformity and available energy and does not determine what happens to remaining generation. Actual electricity consumption changes with operating conditions and needs measurement; hourly totals alone do not establish coincidence throughout an hour.
Before treating the alternative as feasible, specialists must check the timing of flows within each interval, source limits, pump operating points, pressure, protection and the stock needed in the following period. The water-service owner must confirm the user schedule, including the permitted response to a deviation from plan.
What a variable-speed drive can and cannot prove
A variable-speed drive may change motor speed within the capabilities of the actual drive, pump and controls. Operating points, permitted limits and required flow need checking in each mode. A drive does not mean a pump can operate at any low power or that slower speed delivers a predetermined saving.
Ask a specialist to compare pump characteristics with the hydraulic system, source modes and reservoir. Include starts, protection, sensors and communication requirements. Do not change drive settings to follow the sun without an agreed design and tests.
Compare water and electrical schedules
For each permissible water scenario determine an electrical profile from measurement or a justified model. Compare it with PV and other consumers at the same metering boundary. Do not allocate the same solar energy to the pump and the workshop at once. If generation is insufficient, identify the other available source and priority rules.
Check working days, weekends, seasonal water modes, cloudy conditions and unexpected demand changes. If water delivery cannot shift, preserve the required schedule and assess PV using actual coincidence. Operation during a grid outage needs a separate backup design, compatibility assessment and tests.
Compare options for the same water requirement
Preserve the baseline schedule: same period, users, agreed volume and pressure requirements. For an alternative change only the assumption being tested, such as when an existing tank is filled. Changing water demand, pump count and tariff simultaneously would not show which factor caused the difference.
Compare each interval's starting and ending stock as well as the daily total. Equal daily sums can conceal a morning shortage or daytime overflow. Record whether the user schedule was met, which reserve limits applied and whether an acceptable reserve remained for the next day. If starting and ending volumes differ, show the difference alongside the result.
Then compare pumped volume with the electrical meter. When data is insufficient, do not derive a universal kWh per cubic metre from one short test. Different levels, pressures and machine configurations can change operating conditions. Record the mode and meter boundary for each value so an engineer can judge whether the comparison is valid.
Plan for deviations
Define what happens when level falls faster than expected, withdrawal increases or a pump fails to start. Assign responsibility for switching to baseline operation and notifying users. Solar priority must not block agreed water delivery. The design should specify behaviour if level is unavailable or the signal is unreliable.
After a trial, review interval data with the process and energy teams. Compare actual delivery, level, pressure and electricity use with assumptions. Mark gaps and manual interventions. If the model does not reproduce observations, refine the inputs and retest before using it for daily planning.
Before automating the schedule, confirm who can use manual mode, how operators see actual level and where faults are logged. Assign an owner and a communication route to water users. A shifted pumping period must not conceal a shortage on the next shift or move the problem to another tank. Reassess assumptions after changes to piping, pumps or withdrawals.
Agree the tests before commissioning
Record level limits, permitted pump modes, water priority and the response to sensor or communication failure. Agree who owns the hydraulic, electrical and software parts. Tests should confirm required delivery and return to a safe mode, not merely a start command.
Use the ONG Solar services page to provide electrical profiles and agreed permissible pump schedules for the solar assessment. The site's responsible specialists separately verify the water balance, hydraulics and users' delivery requirements. The scope of work and measurements is agreed for the specific site.