Load priorities and shedding in backup power
Energy storage and backup

Load priorities and shedding in backup power

Identify load-group dependencies, agree curtailment and check conditions for restoring groups to operation.

ReadAll Articles
A white desk fan, desk lamp and closed silver laptop against a white background

Table of Contents

Load priorities in backup power define which business functions should be maintained and which may be curtailed by agreement when available resources cannot support everything. Start with the functions, their dependencies and the acceptable consequences of interruption, not a breaker or a battery percentage. Only then can the controlled disconnection and restoration of individual groups be described.

Define functions before assigning groups

With those responsible for operations, describe what must work in backup mode, what may run when resources permit and what may be deferred. Classification depends on the site's task rather than the appliance name. The same lighting can be optional in one area and necessary for safe work in another. Requirements for safety circuits, protective functions and their continuity are determined separately by responsible specialists.

Show every component needed by each function: principal equipment, controls, communications, cooling and auxiliary equipment where needed. A group with a small demand may support another, much larger one. Disconnecting it solely because its name has low priority may stop the main function too. Mark these dependencies on the plan before selecting groups for curtailment.

Separately agree the acceptable interruption and the process state after power is removed. Something that can be deferred before starting cannot necessarily be safely interrupted halfway through. An industrial process may need backup for an orderly shutdown. That task has its own conditions and is not replaced by a general priority list.

Intentional curtailment and protective trips

Controlled curtailment is a previously agreed action on a defined group in a specified mode. A protective trip may occur because of a different event and under the rules of the relevant protection. Do not treat them as interchangeable or assume a planned command will prevent every fault. Required protection, interlocks and signals remain subject to a separate engineering decision.

For each group that might be deferred, record its electrical boundary, who authorizes stopping it, the expected state and how execution is confirmed. A disconnection command and confirmation of actual state are different data. If confirmation is missing, the operator needs to see an uncertain state and follow the agreed procedure rather than assume the group is off.

Do not include safety circuits or necessary interlocks in a general disconnection list using a universal template. Those responsible for the site determine what can be changed in the particular mode. A technical device does not cancel machine manufacturers' requirements or agreed staff procedures.

Power and energy answer different questions

Available power answers how much can be supplied simultaneously at a particular moment. Available energy describes the reserve for operation over time. A group that can be switched on now does not necessarily fit the energy budget for a long interruption. Conversely, enough kWh does not prove that the source can withstand every device starting at once.

Gather data at the same boundary: group operating power, variability, starting conditions and energy available to those loads. Check dependencies and the particular system's conditions. In three-phase backup, total kilowatts are not enough either because an individual output may have its own limit. The article on assessing unequal phase loads addresses that question in more detail.

Allow for changes in source availability and load. The schedule should distinguish measured values, assumptions and short peaks. An unknown outage duration does not turn a forecast into guaranteed reserve. A business also needs an agreed course of action if the reserve proves smaller than expected.

A hypothetical group choice

Imagine three groups on one hypothetical output. Group A, needed for the process, draws 5 kW, deferrable group B draws 2 kW and group C draws 2 kW. Assume constant active power values measured at the same AC boundary. For this scenario assume 8 kW of available power and 24 kWh of available energy at that output boundary. These are invented figures, not equipment specifications.

GroupHypothetical powerAgreed status in example
A5 kWRequired function with its dependencies
B2 kWMay be deferred after confirmation
C2 kWMay run if conditions permit

All three together would require 5 + 2 + 2 = 9 kW, exceeding the hypothetical 8 kW. If the responsible parties have confirmed that B may be deferred and it is actually disconnected, A and C together draw 5 + 2 = 7 kW. At constant demand for three hours that is 7 × 3 = 21 kWh, less than the hypothetical 24 kWh at the same boundary. By comparison the arithmetic demand of all three over three hours would be 27 kWh, but the power condition already prevents treating that mode as feasible.

The example does not establish that a real source will survive the transition or that B may be disconnected. Constant powers, no additional loads and losses already accounted for up to the chosen AC boundary are assumed. Starting transients, phases, delays, measurement quality and switching capability are not calculated. If B supplies cooling or control needed by A, removing it can defeat the required function even when the kilowatt addition is correct.

Who decides and under what conditions

A policy for each group should answer four questions: which event or state starts consideration of curtailment, who may authorize it, how the action is confirmed and what the operator sees. A power-shortage signal and an estimate of remaining energy may require different decisions. A threshold or delay cannot be copied from another site without checking the source, measurements and process.

Agree whether the operator or supported automation acts, and what happens on loss of communications, an unavailable sensor or an unexecuted command. Each case needs a responsible person, an indication and an agreed safe procedure. Do not assume every controller supports the desired algorithm or that a manual command has the same priority in every system.

Manual intervention must have defined authority and conditions for returning to automatic operation. It must not mean bypassing protection or interlocks. Before adopting a policy, agree how to check it with the process owner and electrical personnel. Testing must take place under conditions safe for the site, not during an unprepared interruption of important equipment.

Check that each group can be controlled

A group is easy to mark as deferrable on paper, but the physical layout may combine it with other consumers. Reconcile the list with actual circuits and control equipment. If the existing means cannot separate one load from a required function, mark this as a design constraint. A planned disconnection capability does not mean it has already been implemented.

Ask the supplier of the specific solution to show which data it receives, which groups it can control and how it confirms state. Establish whether those functions operate without an external connection and what happens after a controller restart. Software version, device compatibility and source mode may change the available functions. A screen or relay alone does not demonstrate support for the entire agreed scenario.

If automatic curtailment is unavailable, responsible staff may assess a manual procedure, but only where they have access, authority and time to act. Separately define who receives the notice and checks the result. A manual action may also be too slow for a rapid change, so it should not be presented as a substitute for electrical protection.

Before implementation, compare the event sequence with normal and abnormal site conditions. Request the response not only for the successful case but also for an unknown group state, lost data or a failed command. Agree the test conditions, permitted changes and return to normal operation in advance. Associate results with the actual configuration rather than a generic equipment name.

How to restore groups

Grid return or a brief increase in reserve does not necessarily mean every group can be switched on at once. Source readiness, dependent systems and the process itself need confirmation. The sequence and enabling conditions are established for the particular site. If a group needs prior cooling, communications or staff permission, those conditions must be met before it starts.

To avoid frequent switching near a boundary, a supported system may use different conditions for disconnecting and restoring a group and agreed observation intervals. These are called hysteresis and time delay, but their numerical values are not universal. They must suit the equipment and process. Restoration can be manual or automatic only where the action is supported and permitted.

Record the expected and actual state of each group after a command. If one does not return, that is not a reason to bypass its interlock automatically. Identify the cause, notify the responsible person and follow the response plan. After a change to the electrical layout or process, check whether the previous priorities and dependencies remain valid.

What to prepare for a design discussion

Gather the current diagram, functions and group list, dependencies, acceptable interruptions, measured power profiles and unknown parameters. For each proposed action add the responsible person, confirmation conditions and restoration procedure. Separately identify functions that must remain outside the general curtailment algorithm.

These data can support a solar PV and backup power design discussion. Specialized machine, lighting, generator or IT controls and support for particular devices are agreed separately with the responsible providers. The purpose is to assess the actual capabilities of the equipment and process rather than promise a universal control scheme.