If an illustrative solar transformer quotation lists 1,000/1,250 kVA, ONAN/ONAF, match each figure to its cooling method. In that notation, 1,000 kVA is the rating with natural circulation of oil and air. The 1,250 kVA rating requires the documented forced-air arrangement. Procurement needs two answers from the project team. How much apparent power must the transformer carry in the planned operating state? How much must it carry if forced cooling is unavailable?
What ONAN and ONAF mean
The first two letters describe cooling inside the transformer. The last two describe cooling outside it. Both codes begin with ON, which indicates natural circulation of the oil. In ONAN, air also circulates naturally around the heat-transfer surfaces. In ONAF, fans force air across those surfaces while the oil still circulates naturally. The last letter F in ONAF describes the air side of the cooling arrangement.
The code identifies how the transformer removes heat. The manufacturer assigns the corresponding kVA or MVA ratings to a specific design. Ask for separate ONAN and ONAF figures, together with their stated conditions, when reviewing two bids. If your team is still deciding on construction type, start with the comparison of dry-type and oil-filled solar transformers. The comparison below starts after the project has chosen an oil-filled design.
Read the nameplate and specification together
During procurement, confirm that the ratings table, drawings and quotation describe the same configuration. At delivery, add the serial number and a nameplate photograph to that check. Ask the manufacturer to show paired ratings as separate rows. If the quotation gives only the product family and the largest rating, leave the remaining entries open until the bidder confirms them in writing.
| Field | What to record | Where to check it |
|---|---|---|
| ONAN rating | Apparent power and conditions for natural cooling | Approved specification and nameplate |
| ONAF rating | Apparent power, required cooling stage and fan package | Ratings table and scope of supply |
| Application conditions | Environment, altitude and installation conditions for each mode | Manufacturer documentation and site design |
| Availability of forced air | Auxiliary supply, scope boundaries and confirmed ratings for the scenarios under review | Auxiliary supply drawing and written manufacturer confirmation |
| Acceptance evidence | Cooling stage and rating addressed by the agreed temperature-rise evidence | Acceptance plan and relevant report or test record |
If the nameplate uses percentages, ask for the base value and the figures in kVA. With an explicitly stated base of 1,250 kVA, for example, ratings of 80% and 100% correspond to 1,000 and 1,250 kVA. The conversion depends on the stated base. Keep the applicable conditions next to each entry. If one bid assumes an open site and the other assumes a room with defined ventilation, ask both bidders to address the actual site conditions before comparing the figures.
Where the quote treats fans as an option, check whether the final price includes them and the relevant power and control components. Ask what evidence will support the higher rating for the configuration actually ordered. Keep provision for a future fan installation separate from the rating documented for the current order.
A revised bid may add the fans to the equipment list while still attaching the previous rating schedule. Ask for a coordinated set of documents, with matching configuration identifiers and a clear boundary between factory supply and site equipment.
Which power figure belongs in the comparison
Inverter output in kilowatts and transformer capacity in kilovolt-amperes are different quantities. Use the apparent power that passes through the particular transformer in each operating state. It reflects both active and reactive power. In the illustrative balanced sinusoidal case below, apparent power is S = √(P² + Q²), with P in kW, Q in kvar and S in kVA. The project designer determines the calculation basis and the data needed for the real installation.
List the operating states that could produce different requirements at the transformer. These may include daytime solar generation, import to supply facility loads and a case where forced air is unavailable. When the design allows power flow in both directions, record the direction for each row and ask the manufacturer to confirm that the ratings apply to the specified duty. For the cooling comparison, record apparent power by operating state, site conditions and auxiliary-system availability. Put calculated demand and the manufacturer rating on a common reference basis. If the project has figures for both sides of the transformer, ask the designer which figure belongs in the comparison.
For a self-consumption project, locate the inverters, the loads and the metering point relative to the transformer. Simultaneous generation and consumption on one side can change the flow through it. Record the calculation point and the interval for each peak. If the active and reactive peaks occur at different times, ask for matching intervals or agree a separate conservative design case. That keeps the calculation basis visible in the procurement record.
Worked example with two bids
A hypothetical project compares Bid A, rated at 1,000 kVA ONAN and 1,250 kVA ONAF, with Bid B, rated at 1,250 kVA ONAN. Assume the documents confirm the same site conditions for both bids and that Bid A includes the fans required for its ONAF rating. These figures are illustrative. Within each row, the active and reactive power figures refer to the same point and interval.
| Case | Active and reactive power | Apparent power | Bid A | Bid B |
|---|---|---|---|---|
| Daytime operation | 720 kW and 540 kvar | 900 kVA | Within ONAN rating | Within ONAN rating |
| Peak with forced air available | 960 kW and 720 kvar | 1,200 kVA | Within ONAF rating | Within ONAN rating |
| Same requirement without forced air | 960 kW and 720 kvar | 1,200 kVA | 200 kVA above ONAN rating | Within ONAN rating |
At peak, the calculation gives √(960² + 720²) = 1,200 kVA. The difference between this figure and the highest rating in either bid is 50 kVA. The two bids make that 1,250 kVA available under different cooling conditions. If the project requires 1,200 kVA without forced air, Bid A falls short on its documented ONAN rating. If the project permits a different power requirement in that case, give it a separate row and check it against ONAN. This comparison addresses a single procurement criterion. The project team still assesses design margin, the remaining electrical parameters and the overall suitability of each bid.
Document when forced air is available
Fan availability depends on the supplied arrangement. Ask where the fans and controls obtain power, who supplies each component and what the manufacturer documents for loss of auxiliary power or loss of one fan group. Enter the confirmed rating for each required state, or leave the field open. Two installed fan groups alone do not justify applying the full ONAF rating when one group is unavailable. They also give no basis for dividing the difference between ONAN and ONAF equally between the groups.
Check how air reaches the radiators and leaves the installation at the proposed location. Give the manufacturer a layout showing radiators, walls, fencing and nearby structures. If the site has acoustic constraints, request noise data for the relevant cooling modes. When comparing auxiliary costs, record fan system consumption if the supplier documents it. Keep the stated conditions with those figures so the offers can be compared on the same basis.
Keep two cases side by side in the procurement record. For the normal case, list the required apparent power, the documented rating and the conditions that make it available. For the case without forced air, record the site requirement, the corresponding confirmed rating and the person responsible for open questions. If the rows rely on different quote revisions or installation assumptions, request one coordinated response before a purchasing decision.
Keep different cooling contingencies in separate rows. Fan maintenance, loss of auxiliary supply and loss of one fan group can have different consequences. Record the anticipated duration, the required capacity and the relevant specification clause for each. If a manufacturer states a time or temperature condition, carry it into the same row. This helps the designer distinguish a continuous rating from a separately documented temporary duty before comparing final configurations.
Carry the cooling requirements into acceptance
Include the exact transformer configuration, its ratings table, the list of fan and auxiliary equipment, a dimensioned drawing and the installation conditions in the request. Agree what document will demonstrate thermal performance, which rating and cooling mode it addresses, and how the manufacturer will show that it applies to the delivered design. On delivery, check the serial number and the relevant document revisions. If ratings have changed, compare the latest agreed figures against the project requirements before acceptance.
To discuss solar plant design, start with the single-line diagram, the operating-state power table and the two bid packages. The comparison should leave a record of the apparent power required in each state, the evidence for the corresponding rating and the person responsible for resolving open supply or installation conditions.