Read a PVsyst loss diagram as a sequence of modeled stages, not a list of percentages to add. First establish the report version, period and final energy boundary. Then follow each change from the preceding quantity to the next. This gives a proposal reviewer a practical way to identify the assumptions that support the design and the questions to resolve before approval.
The diagram is a simulation result. It does not measure the operation of a plant that has yet to be built or guarantee its future production. The approach below concerns a grid-connected scenario. A battery system or a different use of energy may have different nodes and a different final boundary.
Start with the report boundary and revision
Ask for the complete report rather than only the page showing the highest annual figure. Record the site, PVsyst version, calculation date, variant name, period and configuration. Note the weather data source, array rating, module layout and inverters separately. When a supplier issues a new revision, retain the earlier one and a description of what changed.
Find the name and units of the final quantity. For example, the PVsyst variable dictionary defines E_Grid as energy injected into the grid. EOutInv is available energy at the inverter output. Those are different boundaries. Where a user load is defined, energy injected into the grid cannot automatically be called the plant's entire production or the business's own consumption.
The annual loss diagram is included in the simulation report. Monthly diagrams are available in detailed results under Predefined graphs. A month can reveal seasonal changes in assumptions or their effects that an annual total conceals. Compare the same period and boundary, and request an explanation of each indicator's scope if the configurations differ.
Follow irradiation into electrical energy
The upper part of a report can show solar irradiation in kWh/m². Horizontal irradiation and irradiation in the collector plane refer to different surfaces. Their values depend on the weather basis and geometry. The difference between them is not automatically an equipment fault or an equipment loss.
The model then accounts for the relevant effects on light reaching the array. A report may include shading, incidence angle and soiling. The exact labels and entries depend on the configuration and model inputs. Ask what geometry, obstruction scene and assumptions support those rows. A zero calls for explanation if the factor was not modeled or evidence for it is missing.
After the transition to the electrical section, look for nodes expressed in kWh. PVsyst describes EArrNom as nominal array energy at standard conditions and the starting point for its array loss assessment. EArrMPP is array energy at the maximum power point after array losses. In the variable dictionary, EArray has a separate definition that accounts for operating-point displacement and is not shown as the same node on the loss diagram. Do not substitute one label for another simply because their names are similar.
Do not subtract kWh/m² from kWh. The transition from light to electrical energy depends on array properties and size as represented by the model. If the report prints rounded figures, a small difference in a hand check can follow from rounding. Request values with greater precision when the discrepancy is material or a node cannot be reconciled.
Worked example: every percentage has a new base
Suppose a fictional section begins with 100,000 kWh of nominal electrical array energy. For teaching purposes, assume four successive changes: temperature -10%, module quality +2%, other array losses -5% and inverter -4%. Every input is invented. None describes a real device or site, and none is a recommended design parameter. The table covers only the specified section between the starting and final node, with no other entries.
| Stage | Before, kWh | Change | After, kWh |
|---|---|---|---|
| Temperature | 100,000 | -10% | 90,000 |
| Module quality | 90,000 | +2% | 91,800 |
| Other array losses | 91,800 | -5% | 87,210 |
| Inverter | 87,210 | -4% | 83,721.6 |
The first step is 100,000 × (1 - 0.10) = 90,000 kWh. Apply the gain to that new base: 90,000 × 1.02 = 91,800. The remaining steps give 91,800 × 0.95 = 87,210 and 87,210 × 0.96 = 83,721.6 kWh. The overall change from the starting node is (83,721.6 / 100,000 - 1) × 100 = -16.2784%.
A simple sum of the signed percentages would give -17%, but that combines changes with different bases and does not reproduce the final energy. PVsyst defines each displayed loss relative to the previous energy quantity. If a report does not print every intermediate value, reconstruct the sequence from a known node while respecting the displayed signs and rounding.
Why a loss entry can represent a gain
Do not assume that every line reduces the quantity. For example, PVsyst's module quality parameter can be a negative loss, representing a gain. In the table above, +2% means a gain relative to the preceding energy. It is not a guarantee that real modules will outperform their rating. Read the sign in the actual report alongside the parameter name and explanation: the sign of a loss parameter and the sign of the diagram's change need context.
Ask for the source and basis of the selected value, its version, and whether it is a default or a project-specific assumption. Do not carry a gain from one report into another without support. Likewise, one large figure does not establish that a component has failed. A diagram reflects the behavior of the specified model, not a diagnosis of an operating plant.
Compare two proposals on the same basis
First make a short record for each model. Compare its period and weather dataset, rated module capacity, orientation, geometry and final energy boundary. Then compare the array, inverters, cable scheme and modeled constraints. When one variant uses a different configuration, the difference between totals does not isolate the effect of a single parameter.
Ask for the basis of significant inputs: the shading scene, soiling assumption, thermal model, module quality parameter and cable lengths. If there is a grid limit or user load, establish where it appears in the report and which energy the result represents. A missing line does not always mean an effect is absent. It may have been disabled, treated differently or omitted from the display for that configuration.
To test one design choice fairly, request a base and a changed variant with the other inputs held constant. Record exactly what changed and why. Compare corresponding nodes in kWh, not only one percentage. If several assumptions change at once, request another variant or record that their separate effects have not been isolated.
Allocation among individual loss lines has limits. PVsyst explains that some contributions cannot be determined completely rigorously and changing one parameter can shift other contributions. A difference between two simulations is therefore a comparison of the defined variants, not a guaranteed saving from replacing one component.
Record a question beside each node
A practical review can use four columns: node name, value and unit, source of the assumption, and question for the report author. For each change, establish whether it is user-defined, calculated or derived from equipment parameters. This does not mean the rows can all be changed independently. The record preserves explanations as an early proposal becomes a final layout.
If two reports have different numbers of lines, compare their main energy nodes and settings before interpreting the discrepancy. One report may present an effect in more detail. Do not transfer a sum of percentages between the tables or treat an absent row as evidence of better conditions. If needed, ask the report author to identify the corresponding variable and parameter in the variant file.
Keep the original model before making refinements. After a change in location, module count or equipment, request a new calculation with its own identifier. An agreed set of inputs and outputs makes it possible to trace the actual design assessed when several updated commercial proposals arrive later.
What to request before design approval
Prepare both complete reports with variant identifiers and a list of differences. Add the agreed output boundary, single-line diagram, layout and explanation of input data. Request machine-readable results with units and enough precision to check nodes without avoidable rounding errors. Keep a separate list of questions the available report does not answer.
During solar plant design, give the package to the team for a like-for-like review and agree the scope of that review. Performance ratio answers a different question and needs its own defined basis. After commissioning, a forecast versus actual comparison requires consistent measurements. A pre-construction diagram helps frame questions about the model and preserve the basis for the decision.