To include solar plant unavailability in a PVsyst forecast, define outage scenarios in time and compare them with the same baseline without those outages. Record the system covered, the start and duration of each period, the weather series and the result boundary. The same number of unavailable hours can produce different energy changes because expected output differs across those hours.
The outages in this calculation are assumptions about the future, and the result depends on the selected event timing and weather. It does not establish actual availability, guarantee a repair time or determine the terms of a service agreement. Request several transparent scenarios when the decision is sensitive to assumed downtime.
Start with the system boundary
PVsyst documentation describes system unavailability as periods when the system is treated as inactive in the model. Specific periods can be defined or generated randomly. Check the functions and format for the project version. The 8.1.6 release notes also describe importing a time series from CSV, so an older interface description may not cover every feature of a newer release.
Record what the variant represents: the whole system or another clearly defined model boundary. Do not treat one inverter's failure as a complete plant shutdown without checking the configuration and the capabilities of the selected modelling method. If partial unavailability is needed, agree with the analyst how the affected part is represented and show the method's limitations.
An actual service indicator is a separate task: define eligible time, status sources, formula and contractual exclusions. The guide to solar plant availability explains that work. The prospective scenarios here do not replace an assessment after an event.
Time and energy have different bases
A time fraction compares downtime duration with a defined period. An energy change compares model results at a defined energy boundary. The percentages cannot be assumed equal simply because they describe the same outage. The baseline may show different output at night, during a cloudy hour and at a sunny noon.
For illustration, take four fictional one-hour intervals in one model. The energy in the table is already expressed at a common output boundary. Assume a complete outage in the selected hour removes exactly that hour's baseline amount and nothing else changes. This is a teaching simplification, not a PVsyst result or a forecast for a Ukrainian plant.
| Interval | No outage, kWh | Outage A, kWh | Outage B, kWh |
|---|---|---|---|
| 1 | 0 | 0 | 0 |
| 2 | 5 | 0 | 5 |
| 3 | 20 | 20 | 0 |
| 4 | 15 | 15 | 15 |
| Total | 40 | 35 | 20 |
Both cases contain one unavailable hour out of four, or 25% of the fictional time. Case A reduces output by 5 kWh, or 12.5% of the 40 kWh baseline. Case B reduces it by 20 kWh, or 50%. These fractions apply only to the four invented hours. They are not annual estimates and do not establish typical losses.
In an actual model the result can depend on more than initial hourly output. System composition, constraints and other settings also matter. The example therefore does not replace another simulation with documented inputs. Do not transfer its numbers to a contract or another plant.
Prepare the baseline and variants
Save the initial file, program version, weather series and full system description. In the baseline, check whether planned outages or an equivalent allowance have already been included. In the next variant add one defined scenario. If the same event is included again in another adjustment after simulation, its effect may be counted twice.
Compare variants with identical modules, inverters, constraints, weather and period. Change only the unavailability scenario when the task is to isolate its effect. For each run retain event dates, durations, boundary and the method used to create the periods. Request interval results if the monthly or annual total is insufficient to reproduce the difference.
When periods are generated randomly, preserve the resulting event sequence and the model variant. One random sequence is only one realization of an assumption. It does not describe every possible failure or prove a loss probability. When comparing equipment alternatives, use an agreed sequence or explain how different random events affect the comparison.
Check an imported time series
If the program version uses an imported series, check its format against that version's documentation. Confirm the time zone, step, interval start and end, units and state values. Clock transitions or a change in source can shift timestamps, so reconcile several documented events with the weather series.
A missing record does not automatically mean either operation or shutdown. Ask for the gap-handling rule and check whether the file covers the required period. If event time has been rounded to an hour, a shorter outage can be represented differently from the original log. Record the rule chosen and do not claim precision that the input does not have.
A planned service window and an unforeseen failure have different origins. In the assumptions table state which window was specified for the test and which is a random scenario. If several causes overlap in one hour, consider the same energy at the same boundary once, rather than adding two complete losses for it.
Read the result alongside the baseline
Compare the absolute change in kWh and the percentage of an explicitly named base. Clarify whether energy is shown at inverter output, the export boundary or another point. Export restrictions and other losses mean different points cannot be substituted without explanation. The guide to the loss diagram helps trace report boundaries.
Do not transfer the modelled percentage directly into a financial conclusion. If self-consumption or energy value changes through the day, it matters when output changed. Purchase terms, options for using surplus and service costs need separate confirmation. An annual total without time information cannot answer each of those questions.
For an actual year, compare forecast and records on matching boundaries and weather conditions. The article on forecast versus actual generation explains why a single difference should not immediately be attributed to downtime. Preserve unknown intervals and distinguish a communication gap from a confirmed equipment state.
Consider the decision before selecting a result
A planned service window may be compared with an alternative window as a sensitivity, provided both are feasible under the actual maintenance plan. The model alone does not authorize a change in safe work procedures or establish when a contractor is available. Agree those constraints with the responsible team before treating either scenario as operationally possible.
If two forecasts report the same percentage of unavailable time, ask whether their events occur in the same hours and whether both cover the same equipment. Different weather years and measurement points also limit comparison. If the reported value cannot be traced to an input schedule and a baseline, retain the difference as an open question.
Where there are insufficient records to support a failure schedule, show that uncertainty. A low, central and high scenario can be useful as a decision range when the values have explicit reasons. They are not a statistical confidence interval merely because three numbers are shown. The owner should see which inputs could change the choice and when they will be reviewed.
Keep a reproducible handover
Provide baseline and changed files, weather data, program version and an event list with provenance. Add the equipment boundary, final-energy definition, monthly result table and the interval data needed for verification. Mark whether the sequence was specified, imported or generated randomly, and list the remaining limitations.
Ask for the scenarios to be revisited when more reliable site information is available. To discuss solar service, give the ONG Solar team the equipment list, available history and the specific question. The analysis method and work scope are agreed for each site. No model replaces the site's safe working procedures.