Capitalising Interest on a Solar Construction Loan
Financing

Capitalising Interest on a Solar Construction Loan

Use IAS 23 to reconcile accruing interest in periods of construction, extended suspension and after substantial readiness.

ReadAll Articles
Solar module beside a calendar and notebook

Table of Contents

A construction loan can continue to incur interest while work on a commercial solar plant is on hold. When a company reports under full IFRS, a charged amount can belong in the cost of a qualifying asset in one period and in finance expense in another. The difference depends on what happened on the project and when. Start with the loan accrual, the work log and evidence of the date when the plant was substantially ready. The bank statement helps reconcile cash, while those other records establish the accounting period for capitalisation.

Check which investment IAS 23 covers

IAS 23 treats borrowing costs directly attributable to acquiring, constructing or producing a qualifying asset as part of that asset’s cost. Other borrowing costs are recognised as an expense. A qualifying asset necessarily takes a substantial period of time to prepare for its intended use or sale. For a solar project, document the activities and elapsed time actually required to bring the installation to its intended operating condition. A turnkey installation and a multistage development can reach readiness through quite different paths. The equipment category, project price and term of the loan cannot establish that an asset qualifies by themselves.

This case uses a dedicated loan for a commercial solar plant that takes a substantial period to prepare and is assessed as one integrated installation. General borrowing needs a separate assessment, including the relevant capitalisation rate and eligible expenditure base. A drawdown establishes when funding became available. To reconcile lender and supplier milestones, use the solar project payment calendar. Retain movement between accounts as a funding detail so that it does not appear as two items of expenditure on the plant.

Under IAS 23, capitalisation starts on the first date when three conditions apply together. The company incurs expenditure on the asset, incurs borrowing costs, and undertakes activities necessary to prepare the asset for its intended use or sale. Check those dates individually. An interest accrual that precedes the first qualifying expenditure may have to remain in period expense even when the loan agreement names the project. Substantive design and administrative work can be relevant before physical installation starts if it is needed to prepare the asset. Record the outputs and how they feed into the construction sequence.

Use the work record to assess a pause

During an extended period in which active development is suspended, IAS 23 requires suspension of borrowing-cost capitalisation. Gather the stop notice, job logs and evidence of any continuing design, tests or necessary administrative work. A contractor's decision to stop work on site may affect only one package. Ask which activities continued for the qualifying asset and whether they materially advanced its preparation. For example, synchronisation design changes that are necessary for intended operation can require substantial engineering work without a construction crew present.

Normal temporary delays that are a necessary part of preparation have different circumstances. Consider an unavoidable waiting stage specific to the construction process. Record the dependency and show why the wait forms part of bringing the asset to its intended use. Procurement or financing disputes can also create a genuine idle period. It takes evidence of which activities continued to decide whether a gap falls in that category. There is no universal number of days in IAS 23 that turns a waiting interval into a qualifying or nonqualifying one.

Write a dated note that covers the first day of the gap, the activity that continued or stopped, the scope affected and the actual return to active development. Preserve comparable evidence for both decisions so a reviewer can test whether similar periods were treated consistently. Consider a scheduled commissioning slot that moves three weeks. That calendar event alone cannot tell you whether the plant still required substantive preparation. The delay could occur while protection settings are being completed, during a genuinely idle hold, or after readiness while the owner arranges a preferred launch date.

Example of a dedicated loan across eight months

Assume a company accrues UAH 50,000 each month from January to August on a loan dedicated to one qualifying solar asset. All amounts are fictional and months are simplified to align with accrual periods. Necessary preparation and project expenditure first overlap with the borrowing cost in February. The company earns UAH 6,000 in February from temporarily investing unused proceeds of that same loan. No other investment income is assumed. April and May are an extended suspension without active development. Work resumes in June, and substantially all necessary preparation is complete by the end of July.

Period and evidenceBorrowing costs incurredIncrease in asset cost
January. Interest before expenditure.UAH 50,000UAH 0
February. Start and temporary investment income.UAH 50,000UAH 44,000
March. Necessary engineering continues.UAH 50,000UAH 50,000
April to May. Extended development suspension.UAH 100,000UAH 0
June to July. Work resumes through readiness.UAH 100,000UAH 100,000
August. Borrowing after readiness.UAH 50,000UAH 0
TotalUAH 400,000UAH 194,000

Under the specific borrowing rule, February contributes UAH 44,000 to asset cost after reducing the eligible UAH 50,000 by UAH 6,000 of income from temporarily investing the specific loan proceeds. March, June and July together contribute UAH 150,000. The January, April, May and August accruals total UAH 200,000 of borrowing costs outside the capitalisation window. Reconcile the gross UAH 400,000 with UAH 194,000 capitalised, UAH 200,000 outside the eligible periods and the UAH 6,000 adjustment to the amount eligible. A real project might stop or resume within a month. Where material, work from supported dates and the borrowing accrual detail instead of applying the example’s full-month buckets.

Keep the lender’s income or debt statement and the entity’s temporary investment record next to the calculation. Identify the source of the deposited funds. The answer can change when the interest comes from ordinary revenue accounts or from deposits whose link to the specific borrowing has not been established. In a long project, keep a schedule with the previous cumulative capitalised amount, the amount added this period and the new balance. That lets another reviewer reproduce the IAS 23 disclosure figure from period schedules.

Fix the end date at substantial readiness

Capitalisation ceases when substantially all activities necessary to prepare the qualifying asset for intended use or sale are complete. Minor modifications or ordinary administrative closeout may remain. Keep a record of which tasks actually prevent intended operation. For instance, a required commissioning test can affect the readiness analysis in the example, whereas organising the archived file afterwards may have no effect. Where project parts can each operate as intended independently, IAS 23 may require earlier cessation for a completed part even while the rest is under construction. Confirm what the infrastructure and actual operating arrangement support.

Give engineering, treasury and accounting a common timeline with distinct fields for physical completion, substantiated readiness, the final contractor payment and the next loan payment. The event that determines the interest cut-off can precede payment of retention or the last finance instalment. The solar asset records reconciliation explains how to hand over equipment records and dates. A short readiness memo can reference specific test records and separate the work still needed from ordinary closeout items.

Reconcile expense, asset cost and cash

Maintain the full interest accrual separately from each cash settlement. A grace period may leave interest payable later or change the lender’s balance. This is another question from how much goes into the solar asset. Compare the applicable loan provisions with the solar loan grace period reconciliation and put treasury payments in their expected periods. Accounting keeps a bridge between the gross accrual, eligible amount and expense so the capitalised figure can be tied to project cost without repeating the financing payment in the model.

At close, retain the dates of the three commencement conditions, evidence of work during each gap, the suspension and resumption analysis, the interest records and the conclusion on readiness. With a general facility or an installation whose parts come online independently, adapt the schedule to the relevant facts. The reporting framework, evidence of work and specific loan terms determine the actual treatment. The example amounts are calculation inputs and can differ across sites, contracts and lenders.