Energy storage under martial law: special procedures
Land, permits and licences

Energy storage under martial law: special procedures

How to check eligibility, safety, deferred formalities and deadlines for an energy storage project under martial law.

8 min estimated reading time

Read articleReturn to the guide
Illustration of an energy storage site with a container, two electrical cabinets, a technical building, a calendar and a work-plan sheet.

In this article

A special procedure for energy storage during martial law allows some land and construction formalities to be deferred, but does not remove the client's subsequent obligations. Applicability depends on the facility's purpose and the current conditions of Resolution 1320. Safety, grid connection and the legal basis for future operation must be checked before implementation begins.

The practical question is not only whether equipment can be installed sooner. Establish which documents may be deferred, what remains mandatory immediately and whether the facility can later be formalized without reconstruction. All three checks belong in one plan.

When the special procedure applies to your project

The resolution covers construction and placement of specified energy installations by businesses, including energy storage and related infrastructure. Conditions are tied to supplying energy to critical infrastructure, social facilities and consumers, including during outages. The word "storage" in a procurement title alone does not establish eligibility.

Record the client, location, equipment, consumers and intended operating modes. Distinguish the storage installation from a solar plant, substation, cable routes and other structures. Do not automatically treat all works on a business's premises as related networks: their relationship to the specific facility must be clear.

Do not rely on an old version solely because a similar project previously used it. Conditions have changed, including equipment coverage. Check the version applicable on the date of the relevant action against the actual configuration and retain the result with the technical brief.

Keep a short change log: decision date, what changed, affected documents and technical parameters, and who checked the consequences. Moving the installation or changing connected consumers requires revisiting the initial questions. This log is a client tool, not an additional state form.

What may be deferred and what remains required

The simplification changes the sequence of certain administrative actions. It does not mean documentation will never be needed. Organize work from the outset around preparation, construction and subsequent formalization.

Deferred formalities and continuing obligations
IssueProcedural featureClient consideration
Planning documentsSpecified works may start without the relevant documentation and planning conditions.Assess in advance whether the facility can be formalized later.
DesignConstruction works may proceed in parallel with design development.Provide technical solutions and subsequently develop and approve the required documentation.
LandUse before the established formalization is possible under special conditions.Obtain the required consent and plan registration of property rights.
Start of operationA special procedure permits operation without a prior construction certificate.Conduct the required comprehensive tests and inform the territorial energy supervision authority.
Completion of formalitiesDeferred actions remain due within the specified period.Plan the schedule, budget and responsible parties for documents, examination and acceptance.

This table organizes the assessment but does not determine eligibility. If a structure or work type is outside the special conditions, establish its own legal basis.

What to check on the site before work starts

Using land before withdrawal, purchase or allocation requires the appropriate party's consent. For private land this is the owner; for state land the relevant regional or Kyiv city military administration; and for municipal land the relevant local self-government body. A verbal arrangement with a site user does not automatically satisfy that condition.

Check protection zones, existing networks, third-party rights and site restrictions. Consent to use land does not prove technical suitability or guarantee completion of later procedures. Installing a container first and discovering afterward that it conflicts with utility routes or required access is particularly risky.

For documentation, review land and planning conditions. Do not confuse deferral under the special procedure with other land-use or design-input rules. Each mechanism has its own conditions and must be assessed separately.

Environmental impact assessment is a separate issue. Do not extend special exceptions for other types of energy facility to every storage installation. Assess the planned activity as a whole, including associated infrastructure and site characteristics. The absence of the storage term from one list does not itself conclude that assessment.

Design and testing remain part of the work

Parallel construction and design do not permit installation without verified technical solutions. Agreed inputs, diagrams, protection, controls and safe maintenance arrangements are needed. Their scope depends on the selected technology, location and operating modes, not a universal checklist for every battery.

Before operation, comprehensive electrical-installation tests are required to the extent of applicable industry requirements. Inform the territorial energy supervision authority of the measures completed. An equipment passport or demonstration that a unit turns on is not equivalent to comprehensive testing of the installed facility.

Separately assess fire, technogenic and industrial safety and whether requirements for high-hazard facilities or work apply. Do not classify every storage installation as such in advance or dismiss those requirements merely because equipment is containerized. Check the installation's composition and operating conditions.

When planning design and acceptance into operation, coordinate documentation with installation. Retain as-built materials, actual equipment details, test results and design changes so the documentation matches the constructed facility.

Link each check in the handover package to the actual diagram and equipment. If protection settings or the scheme change after testing, determine which results need updating. Sending information to the supervisory authority and obtaining a separate positive opinion are different actions: confirm the action actually completed.

How to calculate the deadline for subsequent formalities

For facilities implemented under this procedure, deferred actions must be completed within 24 months after construction or placement is finished, but no later than six months after martial law ends or is revoked. Both limits apply simultaneously. Extension of martial law does not itself stop the period running from completion of a particular facility.

These actions include required land formation and allocation, registration of property rights, development and approval of the design, and obtaining an expert report and certificate according to law. Check the required scope and path early instead of leaving all issues to the final month.

Hypothetical planning example. If a facility is completed in December, its own period begins at that event. If martial law ends before that period expires, the six-month limit also applies. Use the earlier deadline in the project calendar. This explains the logic and does not predict when martial law will end.

Document the start and completion of work and the grounds for applying the special procedure. If rules change, do not assume every future action will automatically be assessed under the old version. Retain the decision history and check requirements at each stage.

Connection, licensing and economics need separate checks

Deferring construction documents does not create available grid capacity. Grid connection still requires checks of the connection point, permitted import and export, metering and relevant operator conditions. The construction procedure does not authorize unilateral changes to grid interaction.

Separately determine whether an energy storage license is required. Participant status, installed capacity, measurement site and applicable exceptions matter. Simplified installation does not replace licensing, market contract or metering readiness checks.

Include the cost of completing formalities, possible design changes and repeat checks in the financial plan. If economics depend on a special tariff, tax or customs regime, check its own criteria and dates. Eligibility to build under one procedure does not automatically establish eligibility for another benefit.

In contractor agreements, separate the cost of technical launch from completing documentation. Check whether preparing examination materials, addressing comments and handing over final documents are included. Otherwise successful equipment activation may be mistaken for completion while part of the agreed scope remains open.

Organize the project without accumulating unresolved issues

  1. Check the basis.Compare purpose, facility scope, land and current conditions of the special procedure.
  2. Run two processes in parallel.Organize technical delivery and documentation with named responsibilities.
  3. Complete deferred actions.Finish required procedures by the applicable deadline and retain evidence.

Before starting, the client should have concise answers to the following checkpoints. They do not replace professional review, but reveal unresolved matters. For each answer retain evidence or a specific next task and owner. "Check later" without a deadline is not a manageable plan. If applicability or the ability to complete formalities is unconfirmed, reconsider the route before work begins. Buying equipment does not resolve these uncertainties.

  • Why does the specific facility meet the special conditions?
  • Who consented to land use and can subsequent formalization be completed?
  • Who is responsible for design decisions, testing and safety?
  • Which grid and licensing procedures are separate?
  • Which documents establish the dates, and who monitors deadlines?

For an initial technical assessment, discuss your project and prepare a description of consumers, the scheme and equipment parameters. The decision to use the special procedure requires review of your actual configuration and documents.