To compare SARAH3 and ERA5 in PVGIS 5.3, run the same fixed solar array twice and change only the solar radiation database. Check that both result files cover the same years before comparing annual and monthly production. At a point in Vinnytsia, the ERA5 run in this example gave 2.65% more average annual energy than SARAH3, yet gave less in June and July. This is the sensitivity of one model to its radiation input. Selecting a basis for a project requires the actual location, the intended array and an explanation of which months influence the decision.
What changes with the database
SARAH3 estimates surface solar irradiance from satellite observations. ERA5 is a reanalysis, a reconstruction of past weather that uses a numerical model and observations. The methods represent clouds and radiation in different ways and work on different spatial grids. A PVGIS result is tied to the selected point and the data available there. A finer grid can describe more spatial detail, while accuracy at the project site needs to be assessed against suitable evidence. The pixel size alone gives no estimate of the error for a particular roof or field.
Keep the version and the database name with the file. For PVGIS 5.3, SARAH3 is the default radiation database over much of the part of Europe it covers. Both radiation choices cover 2005 to 2023 in the example below. A different release can use another period even when the database label looks similar. In the two files for Vinnytsia, the radiation database field changes from PVGIS-SARAH3 to PVGIS-ERA5, while the weather database field reads ERA5 in both. Save the full input record so the source of radiation can still be identified when a report mentions ERA5 in several places.
In the production report, annual irradiation on the module plane is the solar energy received per square metre. Annual PV production is the electrical energy calculated for the modeled system. The figures use different units and answer different questions. A percentage change in plane irradiation can produce a different percentage change in modeled electricity because the conversion calculation also depends on irradiance and temperature. Keep both figures in the worksheet to locate the difference before deciding how much it matters to the project.
Set up comparable runs
Start with the coordinates for the same proposed array and the same version of PVGIS. Select the fixed configuration and enter the agreed tilt and azimuth. Copy the installed peak power, module technology, mounting type, system loss assumption and horizon setting into the second run. Check that angle optimisation is off, since the question here concerns the same array geometry. If a design drawing supplies the direction, use the PVGIS azimuth check to verify the convention before comparing the results. Entering the geometry correctly once helps both runs describe the intended plane.
Read back the years in each export. Two summaries can look comparable because they say PVGIS and list the same capacity, even if one averages a longer historical period. If the years differ, either obtain a pair with the same reported period or arrange a comparison over matching years using historical series and documented aggregation. Preserve the source files and the exact settings before transferring numbers to a spreadsheet. A typical meteorological year and a historical series serve different questions, so keep the chosen type visible in the report.
Use a simple comparison sheet with one column per run and a third column for differences. Record the coordinate precision, the period, the radiation database and the setting for every input that stayed fixed. Compare the same output fields and use a single convention for signs. Here the difference is ERA5 minus SARAH3. If the team chooses to express it as a percentage, divide by the SARAH3 result and label the denominator. Keep the underlying values at their reported precision until the last step. This preserves small differences that would disappear if the runs were rounded to whole numbers first.
For an array with several module groups, record which group each pair of runs represents. Two roof pitches may call for separate agreed angles. Compare the two databases for each group with identical inputs within that pair. Add group production within each scenario when that treatment fits the project model. This makes the contribution of each plane traceable if the overall proposal combines several orientations.
Read the Vinnytsia example
The two PVGIS 5.3 calculations used 49.233° N and 28.467° E, crystalline silicon modules and a peak capacity of 1 kWp. Both modeled a free-standing, fixed array facing due south with a 30° tilt, calculated terrain horizon and 14% entered system losses. Both exports reported 2005 to 2023. The parameters describe a modeling example at those coordinates. The 14% is an input to this comparison and should be replaced with the justified value for another project.
| Metric | SARAH3 | ERA5 |
|---|---|---|
| Annual PV, kWh/year | 1,121.16 | 1,150.85 |
| Annual irradiation, kWh/m²/year | 1,411.18 | 1,432.22 |
| March PV, kWh/month | 90.05 | 106.85 |
| June PV, kWh/month | 142.29 | 137.82 |
| July PV, kWh/month | 144.87 | 140.92 |
The annual production difference is 29.69 kWh, or about 2.65% of the SARAH3 result. The corresponding difference in annual irradiation is 21.04 kWh/m², about 1.49% relative to SARAH3. In March, ERA5 gives 16.80 kWh more for the modeled array. In June it gives 4.47 kWh less, and in July it gives 3.95 kWh less. These are averages for each named month across the historical period. A project that needs energy mainly in summer should inspect the summer rows before relying on a decision based on the annual total.
Read the year-to-year variation separately. The outputs report a standard deviation of annual modeled production of 43.46 kWh for SARAH3 and 28.53 kWh for ERA5. Each figure describes variation across years within that run. The 29.69 kWh gap describes a difference between the runs' annual means. Keep the statistics in separate worksheet columns, because they do not measure the same thing. Their combination alone cannot establish a probability of future underproduction, a guaranteed minimum or a bankable yield estimate.
Keep a design comparison separate
If two proposed layouts differ, repeat the database comparison for each layout. A four-cell worksheet can show layout A with SARAH3 and ERA5 in one row, then layout B with the same two radiation choices in the next. Compare the two values within a row to assess sensitivity to the dataset. Compare values within a column to see the effect of the layout on one common radiation basis. Comparing A with SARAH3 directly against B with ERA5 would combine two changes. If the preferred layout changes between the columns, record that dependence before using production as the deciding criterion.
Use the results in a project
Begin with the part of the proposal that might change. An annual comparison may be adequate for checking why two early estimates disagree. If production in a specific season affects the choice, compare those months and carry each complete set of monthly values forward as a separate case. Using the higher value from each run would construct a third series with no original data source. Averaging the two results would also be a separate assumption. Keep the two runs intact until the design team has documented why it wants to use another method.
A proposal can contain differences unrelated to the radiation database. Check the stated array capacity and the output boundary before attributing the difference to weather. A calculation used to size the array may omit project-specific effects that are treated explicitly in a design report, such as equipment limits, network restrictions or periods when the system is unavailable. Ask where those assumptions enter the model. When comparing forecasts with operating data, use the guide to forecast and measured generation to check the measurement boundary, timing and reasons for a gap.
Hand over both exports, the worksheet and the assumption the decision depends on. Include the source period and the annual and monthly results, with the units written beside the values. Identify whether the documents support a first estimate or are intended to inform a final design. If the database choice would change the decision, ask the solar design team what site information or comparable measurements it needs to justify a baseline. That gives reviewers a clear way to resolve the difference and reproduce the figures later.