To compare measured solar plant data with a PVsyst simulation, choose a pair of quantities at the same energy boundary and for the same intervals. In Measured data, prepare and check the source series, then define the comparison before running the simulation. Report all valid intervals and normal operation as separate samples when both questions matter. Otherwise, the headline difference can reflect the selection of outages and missing readings as much as the yield model.
Preserve the source measurements
Keep the original export from the meter or monitoring platform. Identify the instrument, location, time zone, recording interval and units. For each column, verify whether it contains interval energy, average power or a cumulative register. Converting average power to energy requires the actual interval duration. For cumulative measurements, retain any dates when the meter was reset or replaced. That makes it possible to account for changes in the register before pairing intervals.
Document what each instrument includes. Energy from a group of inverter outputs can differ from grid export because of losses, use on site or the metering arrangement. The model's EOutInv variable concerns energy at the inverter output. E_Grid concerns electricity injected into the grid. Pair each measured series with the model quantity that represents the same boundary. An automatic association based on a similar column name can silently compare different quantities.
Keep the electrical drawing and revision date with the measured data. An expansion or transformer change can alter what a meter includes. A month-end report alone cannot tell the date when the measurement boundary changed. Record the change in the source history and use separate periods if needed. The general forecast versus actual generation review covers why a business estimate can differ from operating data. Here the goal is to construct and verify specific pairs inside the software.
Review the timestamps and inputs
PVsyst Measured data can import prepared text data and associate selected columns with measured quantities. Use its tables and graphical checks to verify the imported data. Look at a few days with complete power and irradiance values. Confirm whether the timestamp labels the start or end of the interval and how any daylight-saving changes were recorded. The PVsyst 8.1 weather timestamp review describes the separate check of the time convention. Incorrect time alignment can affect paired measurements even where the daily sum appears unchanged.
The comparison simulation uses meteorological data from the measurements file. Check that the necessary weather quantities are represented and suitable for the intended analysis. If separately acquired weather data are incorporated, preserve the source and how their measurements were synchronized. Review the effective inputs instead of assuming the typical-year file from the design model still governs that run. Record the file revision and the start date.
Avoid applying an offset solely to make two plots line up. Check the instrument specification, the time zone and the timestamp of events that can be independently identified. Where loggers represent different interval conventions, it can be necessary to reconstruct the comparison from the archived series. If the time basis remains unclear for particular periods, retain a flag for those records. Resolving a timing issue can change the interpretation of multiple intervals without changing the total energy for the day.
Choose the comparison conditions
In PVsyst, associate the measured field with a simulation variable and select the accumulation conditions before running the comparison. Give each set a label indicating its fields, time scale and filters. One set can include all valid measurement pairs while another represents periods when the inverter was running. Filtering out outages helps evaluate model behaviour during operation. The effect of outages on actual delivered energy belongs in a separately reported result when that is the question.
| Record state | Treatment in the review |
|---|---|
| Valid pair for the same interval | Include it in the corresponding sample |
| Verified zero during a shutdown | Include in the full sample and label the state |
| Meter reading missing | Record a gap and exclude the unmatched pair |
| Inconsistent energy boundaries | Correct the pairing or report them separately |
| Uncertain time or equipment state | Retain the record and investigate |
Separate the reason for excluding each interval from the numerical value it would have contributed. A zero during a confirmed stop provides information about operation. A missing reading supplies no value to sum. An export limit or a change in dispatch can create legitimate differences even with valid data. Those cases need their own labels for analysis. For a different question about modelling plant downtime, review the PVsyst system unavailability scenarios.
Work through a paired sample
Take four hypothetical 15-minute intervals for the same AC meter boundary. Simulated energy is 18, 14, 16 and 12 kWh. The first three meter values are 17, 15 and zero kWh, with no measurement in the fourth. A shutdown log confirms the zero in the third interval. These inputs demonstrate a data-handling choice rather than the performance of a site.
For all three valid pairs, metered energy is 32 kWh and simulated energy is 48 kWh. The measured-minus-modelled difference is -16 kWh, approximately -33.3% of the simulated 48 kWh. For the two confirmed generating intervals, both sums are 32 kWh. The individual differences were still minus 1 kWh and plus 1 kWh. One positive and one negative difference cancelled in the total. Including the fourth simulated value yields 60 kWh, which represents a different interval set from the metered sample.
Report the number of pairs with the result. Here the full valid sample includes three of four intervals, and the normal-operation sample includes two. This distinction matters when an estimate is limited by data availability. Review which hours or operating states show repeated deviations. The two intervals with equal sums cannot establish annual model accuracy. Plotting or tabulating the interval errors can reveal patterns that disappear when calculating an aggregate.
Keep diagnostic and project outcomes distinct
A model that follows normal operating points may still differ from annual production when site downtime is substantial. Conversely, a matching monthly total can combine overestimation in one mode with underestimation in another. Keep a documented sample for normal operation and a separate result covering valid records of overall operation. If the available equipment log is incomplete, report that uncertainty. Retaining the original and filtered views lets another reviewer check the selection without treating temporary exclusions as permanent changes to the historical evidence.
Reconcile the equipment log and the meter map
A group of inverters can still produce energy when one unit is stopped or one meter stops communicating. Identify the device boundary before tagging an interval. Preserve the reason for each exclusion and make it possible to distinguish an incomplete reading from a valid measurement retained for a different operating-state analysis. A count of included records by state helps explain which daily or seasonal comparisons the data support.
If several readings feed the same export, check whether a central meter already includes downstream counters. Adding a submeter to the central value would count part of the energy twice. Keep the drawing, identifier and aggregation rule next to the columns. When an export changes from cumulative energy to interval power, verify units and reconstruct the paired series before importing it. Test the updated importer against a short interval with known behaviour and at least one flagged record.
Make the review reproducible
Preserve the raw export, transformation notes, simulation variant and filters. Store the instrument map and equipment log beside them. State the date range and the pairing rule for each conclusion. If a source field has been estimated, keep a separate flag. A comparison report should make it possible to recover both the complete evidence and the narrower sample used for a diagnostic question.
For commercial solar design or a review of an operating plant, provide the current layout and a dated list of configuration changes. The location, equipment, weather record and meter boundary affect the result. The handover should identify what the paired run can explain, where more measurement is needed and which input files will allow the engineering team to reproduce the calculation.