PVGIS 5.3 offers two performance models for crystalline silicon. The original option uses the earlier coefficients. The crystalline silicon (2025) option represents a newer set of module measurements across irradiance and temperature conditions. For an early commercial yield estimate, record which model was used and compare both with the other project inputs held fixed. The result shows whether this modelling choice matters to the proposal and what evidence is needed for the next estimate.
What changes between the two options
The 2025 option uses a different set of coefficients in the equation for module power. The coefficients were fitted to measurements that include more recent crystalline silicon products. Changing the set changes the model response to irradiance and module temperature. The installed peak power remains a separate input. At the same entered capacity, the models describe different departures from the standard reference conditions.
The label crystalline silicon (2025) identifies the coefficient set. It does not describe the manufacturing date of each module. Its fit represents a sample of products rather than the measured performance of every individual technology or variant offered. An estimate for an exact equipment choice still depends on the model identifier, its documented performance and the electrical configuration. A broadly matching technology class can be a reasonable basis for a screening case before specific components are selected.
The original crystalline silicon coefficients remain the default for PVGIS 5.3. If an older worksheet says only “crystalline silicon”, look at the saved inputs to determine which option was used. In the corresponding PVcalc API, crystSi and crystSi2025 identify the options. When repeating a calculation, preserve the version of the service and its actual input values. Save the technology label and request code with the retrieval date so the reviewer can reconstruct the comparison later.
How to interpret an operating point
The power equation relates standard-test power to in-plane irradiance and module temperature. It uses irradiance relative to 1,000 W/m² and the difference between module temperature and 25 °C. At 1,000 W/m² and 25 °C the adjustment terms have no contribution. The two coefficient sets therefore give the same peak power at that standard point for the same entered capacity. They can diverge when conditions move away from that reference.
Take an illustrative 100 kWp array and evaluate three specified conditions with the published coefficients. Both models use the same irradiance and module temperature in each row. The figures show DC power at the module equation boundary before any inverter, cable or site-level reduction. This calculation uses no site weather, geographical assumptions or individual product specifications. Its purpose is to show the scale and meaning of the change at each selected operating point.
| Condition | Original, kW | 2025, kW |
|---|---|---|
| 1,000 W/m², 25 °C | 100.000 | 100.000 |
| 200 W/m², 25 °C | 18.459 | 19.366 |
| 1,000 W/m², 55 °C | 86.344 | 90.955 |
At 200 W/m², simple proportional scaling gives 20 kW. The relative efficiency multipliers at 25 °C are about 0.92293 and 0.96828. Applying them gives the two values shown. At 1,000 W/m² and 55 °C the logarithmic terms vanish, leaving the temperature terms as the reason for the different result. This provides a reproducible way to tell which inputs and equations are being compared before using a longer time series.
One operating point provides no annual energy total. The array spends different amounts of time in different conditions. At high irradiance, inverter limits might prevent part of the available DC power from reaching the meter. In lower irradiance, shading patterns and the site operating schedule may matter. To quantify an annual effect useful to a particular business, define the final energy boundary and consider when the site can use the generation.
Set up a matched pair
Run both options for the same location, irradiation database, tilt, azimuth, installed rating and horizon treatment. Preserve the choice of mounting and system loss as well. Change PV technology between the runs and use file names that identify the option. Report daily, monthly or annual quantities at the same boundary with consistent units and rounding. This keeps a model comparison from becoming a comparison of two different site designs.
Choosing a resource dataset changes what weather the model receives. Choosing the crystalline silicon coefficients changes how it translates that weather into power. For a SARAH3 versus ERA5 comparison, retain the same technology option. When testing the coefficients, keep the dataset fixed. If the assumed module mounting changes, compare that effect separately, since mounting and airflow affect the temperature calculation. Documenting these scenarios in a small table makes the cause of each result easier to identify.
Compare annual energy and monthly differences. Calculate any percentage against an identified baseline. If most of an annual difference appears in the summer, report which months account for it. An owner whose electricity demand is highest in the winter will interpret that result differently from one whose demand follows a summer production schedule. A monthly check can help narrow the next question, while an energy-use model still needs matching generation and demand intervals where the decision depends on coincidence.
Relate the coefficient set to the offered product
Ask for the precise module designation and revision. Check the standard-test power, temperature coefficient and any measured irradiance dependence. Confirm the conditions and tested variant when these data appear in a report. Names such as PERC or HJT describe aspects of the cell technology. They do not provide the six performance coefficients for the exact proposed product. If the switching sensitivity is material, gather stronger evidence before treating it as a difference between two offers. The article on checking a PVsyst PAN file covers the separate validation of a component-specific model.
For a plant that already operates, avoid choosing a coefficient set solely for its fit to one monthly meter result. Align the reporting boundary and periods, check the weather and account for recorded downtime. A close match from one month might reflect a combination of resource conditions and other assumptions. A wider assessment with defined operating periods provides a better basis for testing the estimate. Retain the original model and its inputs even if a documented revision is later accepted.
Separate the power assumption from the product choice
A roof can fit different numbers of modules when the proposed dimensions change. Start with the same DC capacity to isolate the coefficients. Then compare the actual layouts separately and report any change in capacity. This distinction prevents an increase in installed kWp from being attributed to the 2025 performance model. If two roofs share an inverter or an export limit, check the timing of both generation series before treating their separate energy estimates as a combined output.
Keep a reproducibility case for one operating point and a copy of the complete tool output. A calculation at 1,000 W/m² and 55 °C, for instance, can reveal a mistaken substitution of air temperature for module temperature. A later run from another software release should get its own date and version record. With both outputs present, a reviewer can distinguish a change in coefficients from a change in source data or the calculation process.
Keep the decision traceable
Include the software version, technology option, nominal rating, resource dataset and period in the project file. Save the fixed geometry, mounting, losses, horizon and other inputs alongside both results. Identify the equipment documentation used and the point at which the exact module will be confirmed. Until then, show the effect as a sensitivity. If it changes the commercial decision, keep both cases available for the subsequent design review.
For commercial solar design, add the equipment records, array layout and interval load profile if on-site use matters to the business case. The choice of coefficient set helps quantify how a screening estimate responds to a model assumption. Project results still depend on the site, the identified modules and the installed configuration. The handover should show which inputs came from equipment documents and which are still awaiting confirmation.